9612 N DORRINGTON AVE 91331
Certificate Information: 9612 N DORRINGTON AVE 91331
- Application / Permit
- 24010-20000-03708
- Plan Check / Job No.
- B24VN15243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY (27'-6" X 19'-6") ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) -(d)
- Permit Issued
- Issued on 6/6/2025
- Issuing Office
- Current Status
- CofO Issued on 1/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 9/14/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 10/1/2024 | DAWN MC NULTY |
| Building Plans Picked Up | 11/6/2024 | APPLICANT |
| Applicant returned to address corrections | 2/19/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 4/14/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 6/6/2025 | VAHAN JIVALAGIAN |
| Issued | 6/6/2025 | APPLICANT |
| CofO in Progress | 12/16/2025 | MICHEL ABAJAN |
| No Progress | 1/5/2026 | MICHEL ABAJAN |
| CofO in Progress | 1/5/2026 | MICHEL ABAJAN |
| Permit Finaled | 1/29/2026 | RUBEN SALAS |
| CofO Issued | 1/29/2026 | RUBEN SALAS |
| Permit Finaled | 1/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/28/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 3/28/2025 | GEVORK KARAPETYAN |
| Address approval | Cleared | 5/13/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/13/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/14/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jalalpour,, Mohammad; Lic. No.: S6696 | 2610 VISTA DEL ORO NEWPORT BEACH, CA 92660 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/23/2025 | Partial Approval | MICHEL ABAJAN |
| Sewer | 6/23/2025 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 7/2/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/2/2025 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 7/2/2025 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/24/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/24/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Wood Construction | 7/29/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/12/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 9/12/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 9/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/15/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 9/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 9/26/2025 | Corrections Issued | MICHAEL CORTEZ |
| Drywall Nailing | 9/29/2025 | Corrections Issued | MICHAEL CORTEZ |
| Shower Pan | 9/29/2025 | Corrections Issued | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 10/1/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 10/1/2025 | Approved | MICHAEL CORTEZ |
| Pre-Inspection | 11/14/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/9/2025 | Approved | MICHEL ABAJAN |
| Final | 12/9/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/9/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/9/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/9/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 12/9/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 12/9/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/15/2025 | Approved | MICHEL ABAJAN |
| Final | 12/15/2025 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 12/15/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/15/2025 | Approved | MICHEL ABAJAN |
| Service/Power Release | 12/15/2025 | Approved | MICHEL ABAJAN |