9612 N DORRINGTON AVE 91331

Certificate Information: 9612 N DORRINGTON AVE 91331

Application / Permit
24010-20000-03708
Plan Check / Job No.
B24VN15243
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (27'-6" X 19'-6") ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) -(d)
Permit Issued
Issued on 6/6/2025
Issuing Office
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 VAHAN JIVALAGIAN
Corrections Issued 9/14/2024 VAHAN JIVALAGIAN
Quality Review Completed 10/1/2024 DAWN MC NULTY
Building Plans Picked Up 11/6/2024 APPLICANT
Applicant returned to address corrections 2/19/2025 VAHAN JIVALAGIAN
Applicant returned to address corrections 4/14/2025 RAPHAEL ROSAS
Plan Check Approved 6/6/2025 VAHAN JIVALAGIAN
Issued 6/6/2025 APPLICANT
CofO in Progress 12/16/2025 MICHEL ABAJAN
No Progress 1/5/2026 MICHEL ABAJAN
CofO in Progress 1/5/2026 MICHEL ABAJAN
Permit Finaled 1/29/2026 RUBEN SALAS
CofO Issued 1/29/2026 RUBEN SALAS
Permit Finaled 1/29/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 3/28/2025 GEVORK KARAPETYAN
Construction within easement Cleared 3/28/2025 GEVORK KARAPETYAN
Address approval Cleared 5/13/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 5/13/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 5/14/2025 MICHAEL BROWN
Sewer availability Cleared 5/14/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Jalalpour,, Mohammad; Lic. No.: S6696 2610 VISTA DEL ORO      NEWPORT BEACH, CA 92660

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 6/23/2025 Partial Approval MICHEL ABAJAN
Sewer 6/23/2025 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 7/2/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 7/2/2025 Approved MICHEL ABAJAN
Pre-Inspection 7/2/2025 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 7/24/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/24/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/24/2025 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 7/24/2025 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Wood Construction 7/29/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 9/12/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 9/12/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/15/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 9/15/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 9/15/2025 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 9/15/2025 Approved NICHOLAS TROWBRIDGE
Insulation 9/24/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 9/26/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 9/29/2025 Corrections Issued MICHAEL CORTEZ
Shower Pan 9/29/2025 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 9/30/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 9/30/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 10/1/2025 Approved MICHAEL CORTEZ
Shower Pan 10/1/2025 Approved MICHAEL CORTEZ
Pre-Inspection 11/14/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/9/2025 Approved MICHEL ABAJAN
Final 12/9/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 12/9/2025 Approved MICHEL ABAJAN
HVAC-Final 12/9/2025 Approved MICHEL ABAJAN
PLUMBING-Final 12/9/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 12/9/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 12/9/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/15/2025 Approved MICHEL ABAJAN
Final 12/15/2025 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 12/15/2025 Approved MICHEL ABAJAN
PLUMBING-Final 12/15/2025 Approved MICHEL ABAJAN
Service/Power Release 12/15/2025 Approved MICHEL ABAJAN