454 1/4 W 59TH PL 90003
Certificate Information: 454 1/4 W 59TH PL 90003
- Application / Permit
- 24010-20000-03706
- Plan Check / Job No.
- B24VN15239
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 1/13/2026
- Issuing Office
- Current Status
- Issued on 1/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | KEVIN MORALES |
| Corrections Issued | 10/1/2024 | KEVIN MORALES |
| Quality Review Completed | 10/2/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/11/2024 | KEVIN MORALES |
| Plan Check Approved | 9/29/2025 | KEVIN MORALES |
| Issued | 1/13/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 12/31/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 1/3/2025 | JESSICA OPINION |
Contact Information
| Contractor | Teo'S Construction; Lic. No.: 778080-B | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2026 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 2/9/2026 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 2/27/2026 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 2/27/2026 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/9/2026 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 3/11/2026 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Partial Approval | RAUL BARAJAS |