8418 N WILBUR AVE 91324

Certificate Information: 8418 N WILBUR AVE 91324

Application / Permit
24010-20000-03691
Plan Check / Job No.
B24VN15142
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 18'-0" X 24'-0" DETACHED PATIO PER ENGINEERING.
Permit Issued
Issued on 9/16/2024
Issuing Office
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2024 APPLICANT
Assigned to Plan Check Engineer 9/6/2024 ARTIN ZARUKIAN
Corrections Issued 9/7/2024 ARTIN ZARUKIAN
Building Plans Picked Up 9/9/2024 APPLICANT
Issued 9/16/2024 APPLICANT
CofO in Progress 2/6/2025 KRISTEN BEVERIDGE
Permit Finaled 2/12/2025 JOHN JANSON
CofO Issued 2/12/2025 JOHN JANSON
Permit Finaled 2/12/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/10/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 9/11/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Saberi,, Masoud; Lic. No.: C71553 1438 25TH ST APT 4      SANTA MONICA, CA 90404

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2024 Partial Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 11/1/2024 Partial Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 11/6/2024 Corrections Issued DAVID SCANTLIN
Green Building Rough 11/20/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/27/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 12/11/2024 Approved KRISTEN CAUSEY
Drywall Nailing 12/24/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 1/28/2025 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 1/28/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/6/2025 Approved KRISTEN CAUSEY
Final 2/6/2025 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 2/6/2025 Approved KRISTEN CAUSEY