19352 W LANARK ST 91335
Certificate Information: 19352 W LANARK ST 91335
- Application / Permit
- 24010-20000-03665
- Plan Check / Job No.
- B24VN15063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: 1 NEW ADU PER LAMC 12.22 A.33(c) AND (d) ***SEE COMMENTS***
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/9/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/4/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 11/8/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 4/17/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/16/2025 | JOHNPAUL ISIP |
| Issued | 5/20/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | ARUTYUN MADATYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/1/2024 | RYAN CASTRO |
| Low Impact Development (LID) | Cleared | 10/17/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/6/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 2/13/2025 | GEVORK KARAPETYAN |
| Disturb/Remove Protected Trees | Cleared | 2/26/2025 | BRANDON WONG |
| Address approval | Cleared | 5/15/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Susan Development And Construction Inc; Lic. No.: 1089492-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/5/2025 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/11/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 10/3/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 10/3/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/3/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/23/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 12/8/2025 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 12/8/2025 | Approved | MORRIS JACKSON |
| Insulation | 12/11/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Insulation | 12/16/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 12/16/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 12/16/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 12/23/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 5/13/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 5/13/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 5/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 5/13/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/19/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/19/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 5/19/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/19/2026 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/19/2026 | Approved | ARUTYUN MADATYAN |