16113 W DEVONSHIRE ST 91344

Certificate Information: 16113 W DEVONSHIRE ST 91344

Application / Permit
24010-20000-03645
Plan Check / Job No.
B24VN14783
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED 4-CAR GARAGE PER LAMC 12.22A.33(c)-(d). SOLAR INSTALLATION REQUIRED TO MEET 2.1KW PER TITLE 24 PRIOR TO COFO.
Permit Issued
Issued on 5/8/2025
Issuing Office
Current Status
Issued on 5/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 VIVIAN LAO
Corrections Issued 9/16/2024 VIVIAN LAO
Quality Review Completed 9/18/2024 GARO TELMI
Applicant returned to address corrections 2/28/2025 VIVIAN LAO
Applicant returned to address corrections 4/17/2025 VIVIAN LAO
Applicant returned to address corrections 4/18/2025 VIVIAN LAO
Plan Check Approved 5/7/2025 VIVIAN LAO
Issued 5/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/18/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 12/18/2024 CARLOS RAMIREZ
Sewer availability Cleared 12/18/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/6/2025 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khansa,, Eyass; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Interior/Exterior Lathing 6/8/2026   

Inspection Request History

Pre-Inspection 6/30/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 6/30/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 7/2/2025 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/11/2025 Corrections Issued KEVIN BERBERYAN
Deck 8/6/2025 Partial Approval MISAEL ESPARZA
Wood Frame 8/6/2025 Partial Approval MISAEL ESPARZA
Pre-Inspection 9/10/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/24/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/8/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 10/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 10/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 10/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/28/2025 Corrections Issued LOUIS ESCOTO
PLUMBING-Rough 10/30/2025 Approved CHRISTOPHER ROJAS
Shower Pan 11/12/2025 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/22/2026 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/6/2026 Corrections Issued KIRK SANDERS
HVAC-Final 2/6/2026 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 2/25/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/25/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 2/25/2026 Approved CHRISTOPHER ROJAS
Grounding or Bonding 2/25/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 2/25/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/2/2026 Approved KEVIN BERBERYAN
Special/Order Compliance 3/5/2026 Corrections Issued CHRISTOPHER ROJAS
Insulation 4/1/2026 Corrections Issued CHRISTOPHER ROJAS
Insulation 4/16/2026 Approved CHRISTOPHER ROJAS