15935 W VALERIO ST 91406

Certificate Information: 15935 W VALERIO ST 91406

Application / Permit
24010-20000-03624
Plan Check / Job No.
B24VN14710
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) CONVERT (E) 20' X 20' DETACHED GARAGE TO PORTION OF SFD AND ADD NEW 44'8" X 25' TWO STORIES SFD UNIT PER SB9 WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 RARES BODEA
Corrections Issued 9/16/2024 RARES BODEA
Quality Review Completed 9/18/2024 STEVEN KIM
Building Plans Picked Up 9/19/2024 APPLICANT
Applicant returned to address corrections 1/6/2025 RARES BODEA
Applicant returned to address corrections 2/3/2025 RARES BODEA
Plan Check Approved 2/5/2025 RARES BODEA
Issued 2/5/2025 APPLICANT
CofO in Progress 10/2/2025 GAREN HAYRAPETYAN
Permit Finaled 10/7/2025 RUBEN SALAS
CofO Issued 10/7/2025 RUBEN SALAS
Permit Finaled 10/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/16/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 9/24/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 12/16/2024 CARLOS AGUILERA
Sewer availability Cleared 12/16/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/3/2025 CARLOS AGUILERA
Senate Bill 9 Cleared 1/8/2025 ALEX VELA
Hydrant and Access approval Cleared 1/21/2025 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2025 Approved GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 2/24/2025 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 2/27/2025 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 3/3/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/3/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 3/3/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Inspection SALVADOR MARTINEZ
Deputy Wood Construction 3/21/2025 Conditional Approval RAUL OLAGI
Sewer 3/21/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 4/7/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval GAREN HAYRAPETYAN
HVAC-Rough 4/14/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/18/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/22/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 4/25/2025 Approved SALVADOR MARTINEZ
Deputy Wood Construction 4/28/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/5/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/5/2025 Not Ready for Inspection SALVADOR MARTINEZ
Verify Sprinkler Sign Off 5/5/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/12/2025 Conditional Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 5/12/2025 Partial Approval SALVADOR MARTINEZ
Shower Pan 5/12/2025 Approved SALVADOR MARTINEZ
Insulation 5/15/2025 Partial Approval MICHAEL CORTEZ
Insulation 5/19/2025 Approved MICHAEL CORTEZ
Drywall Nailing 5/21/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 5/21/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/23/2025 Approved MICHAEL CORTEZ
Underground Mechanical 7/29/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 8/8/2025 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 9/19/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 9/19/2025 Approved GAREN HAYRAPETYAN
Green Building Final 9/19/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Service/Power Release 9/19/2025 Corrections Issued GAREN HAYRAPETYAN
Smoke Detectors 9/19/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 9/25/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 9/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/25/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/2/2025 Approved GAREN HAYRAPETYAN
Final 10/2/2025 OK to Issue CofO GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 10/2/2025 Approved GAREN HAYRAPETYAN