11511 N LEXICON AVE 91342

Certificate Information: 11511 N LEXICON AVE 91342

Application / Permit
24010-20000-03618
Plan Check / Job No.
B24VN14650
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'6" X 43' DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC12.22A.33(b)(1), WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 9/3/2024 MADISON ODELL
Corrections Issued 9/4/2024 MADISON ODELL
Applicant returned to address corrections 2/13/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/19/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 2/25/2025 ARAMIK SHAHMIRZAIAN
Issued 3/5/2025 APPLICANT
CofO in Progress 9/12/2025 MICHEL ABAJAN
Permit Finaled 9/24/2025 RUBEN SALAS
CofO Issued 9/24/2025 RUBEN SALAS
Permit Finaled 9/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/18/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/18/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 12/31/2024 RIDWAN HARDY
Construction within easement Cleared 12/31/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/7/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 1/7/2025 CHARLES POWELL
GPI Written Notices Cleared 2/25/2025 MADISON O'DELL

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Elden, Alexander; Lic. No.: C71696 2415 FORDHAM DR      COSTA MESA, CA 92626

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 3/28/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 4/7/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 5/14/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/14/2025 Approved MICHEL ABAJAN
HVAC-Rough 5/14/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 5/14/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 5/14/2025 Approved MICHEL ABAJAN
Insulation 5/29/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/29/2025 Partial Approval MICHAEL CORTEZ
Drywall Nailing 6/5/2025 Approved MICHAEL CORTEZ
Shower Pan 6/5/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/23/2025 Approved NICHOLAS TROWBRIDGE
Sewer 7/31/2025 Not Ready for Inspection MICHEL ABAJAN
Underground Mechanical 7/31/2025 Partial Approval MICHEL ABAJAN
Sewer 8/5/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/3/2025 Approved MICHEL ABAJAN
Final 9/3/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 9/3/2025 Approved MICHEL ABAJAN
PLUMBING-Final 9/3/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 9/3/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 9/3/2025 Approved MICHEL ABAJAN
Final 9/8/2025 Corrections Issued MICHEL ABAJAN
Service/Power Release 9/8/2025 Not Ready for Inspection MICHEL ABAJAN
Final 9/12/2025 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 9/12/2025 Approved MICHEL ABAJAN