13271 1/2 W DYER ST 91342
Certificate Information: 13271 1/2 W DYER ST 91342
- Application / Permit
- 24010-20000-03548
- Plan Check / Job No.
- B24VN14132
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: new detached 1-story 672 S.F. single family dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21per SB9 Two-Unit Development Ca Govt Code 65852.21 Fire sprinklered NFPA 13D thru out WORK PER WFPP
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- Issued on 3/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | JAD BASMA |
| Corrections Issued | 8/24/2024 | JAD BASMA |
| Quality Review Completed | 8/27/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/11/2025 | JAD BASMA |
| Plan Check Approved | 3/20/2025 | JAD BASMA |
| Issued | 3/21/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/3/2024 | GERMAN RODRIGUEZ MENDOZA |
| Address approval | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 9/24/2024 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 12/10/2024 | KURT CORRAL |
| Construction near power lines | Cleared | 1/23/2025 | GEVORK KARAPETYAN |
| GPI Written Notices | Cleared | 3/20/2025 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2025 | Partial Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 4/1/2025 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 4/16/2025 | Corrections Issued | KEVIN BERBERYAN |
| Wood Frame | 5/13/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/5/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/5/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/5/2025 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 6/5/2025 | Approved | KEVIN BERBERYAN |
| Wood Frame | 6/5/2025 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/9/2025 | No Access for Inspection | LOUIS ESCOTO |
| Shower Pan | 6/9/2025 | No Access for Inspection | LOUIS ESCOTO |
| Interior/Exterior Lathing | 6/11/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 6/11/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 6/12/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/17/2025 | Approved | KEVIN BERBERYAN |