4209 N COSTELLO AVE 91423

Certificate Information: 4209 N COSTELLO AVE 91423

Application / Permit
24010-20000-03545
Plan Check / Job No.
B24VN14121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 100'5-1/16" X 38' TWO STORY SFD WITH HABITABLE BASEMENT AND WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/21/2025
Issuing Office
Valley
Current Status
Issued on 3/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/22/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 RARES BODEA
Corrections Issued 9/12/2024 RARES BODEA
Quality Review Completed 9/18/2024 STEVEN KIM
Building Plans Picked Up 9/19/2024 APPLICANT
Applicant returned to address corrections 2/27/2025 RARES BODEA
Applicant returned to address corrections 3/17/2025 RARES BODEA
Plan Check Approved 3/21/2025 RARES BODEA
Issued 3/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/24/2024 RYAN CASTRO
Low Impact Development Cleared 9/25/2024 LUIS LUVANO
Hydrant and Access approval Cleared 12/16/2024 JERRY KAO
GPI Written Notices Cleared 2/27/2025 RARES BODEA
Grading Pre-Inspection Cleared 2/27/2025 RARES BODEA
Sewer availability Cleared 3/4/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/5/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 3/9/2025 RYAN CASTRO

Contact Information

Contractor Urban Culture Design And Development; Lic. No.: 1126457-B       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/9/2025 Corrections Issued MISAEL ESPARZA
Deputy Reinf. Concrete 4/14/2025 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 5/27/2025 Corrections Issued MISAEL ESPARZA
Underground Mechanical 5/29/2025 Partial Approval JACK KARGODORIAN
Underground Mechanical 6/5/2025 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 6/26/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/30/2025 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 7/3/2025 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 7/22/2025 Conditional Approval JUAN VALENZUELA
Reinforced Concrete Frame 7/22/2025 Approved KEVIN BERBERYAN
Deputy Shotcrete 7/23/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Partial Approval MISAEL ESPARZA
Wood Frame 8/14/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 10/3/2025 Conditional Approval JUAN VALENZUELA
Masonry Wall/Backfill 12/11/2025 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 12/11/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/15/2025 Approved MISAEL ESPARZA
Reinforced Masonry Frame 12/29/2025 Partial Approval MISAEL ESPARZA
Wood Frame 1/8/2026 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 1/28/2026 Approved MISAEL ESPARZA
HVAC-Rough 2/4/2026 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 2/4/2026 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 2/6/2026 Partial Approval MISAEL ESPARZA
Insulation 2/18/2026 No Access for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 2/26/2026 Corrections Issued MISAEL ESPARZA
Insulation 2/26/2026 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/5/2026 Conditional Approval MISAEL ESPARZA
Insulation 3/5/2026 Conditional Approval MISAEL ESPARZA
Special/Order Compliance 3/5/2026 Partial Inspection RAUL OLAGI
Drywall Nailing 3/17/2026 Approved MISAEL ESPARZA
Green Building Rough 3/17/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/11/2026 Approved MISAEL ESPARZA
Shower Pan 5/11/2026 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 6/2/2026 Partial Approval MISAEL ESPARZA