9754 N LARAMIE AVE 91311

Certificate Information: 9754 N LARAMIE AVE 91311

Application / Permit
24010-20000-03539
Plan Check / Job No.
B24VN14089
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-6" X 40'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. <ALL ELECTRIC BUILDING> SEE COMMENTS.
Permit Issued
Issued on 12/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 ARTIN ZARUKIAN
Corrections Issued 9/4/2024 ARTIN ZARUKIAN
Building Plans Picked Up 9/5/2024 APPLICANT
Plan Check Approved 12/20/2024 HAYATO TSUCHIYA
Issued 12/20/2024 APPLICANT
CofO in Progress 7/1/2025 DAVID SCANTLIN
Permit Finaled 9/19/2025 JOHN JANSON
CofO Issued 9/19/2025 JOHN JANSON
Permit Finaled 9/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/6/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/6/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 9/6/2024 TAL SHEMEN
Sewer availability Cleared 9/6/2024 TAL SHEMEN
Construction near power lines Cleared 12/4/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2025 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 1/10/2025 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 1/16/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/27/2025 Approved DAVID SCANTLIN
Green Building Rough 2/27/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 2/27/2025 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 2/27/2025 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 2/27/2025 Approved DAVID SCANTLIN
Insulation 3/7/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/7/2025 Approved DAVID SCANTLIN
Shower Pan 3/7/2025 Approved DAVID SCANTLIN
Drywall Nailing 3/13/2025 Approved DAVID SCANTLIN
Final 6/4/2025 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 6/4/2025 Approved DAVID SCANTLIN
Green Building Final 6/4/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 6/4/2025 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 6/4/2025 Approved DAVID SCANTLIN
Final 6/30/2025 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 6/30/2025 Approved DAVID SCANTLIN