284 E 47TH ST 90011
Certificate Information: 284 E 47TH ST 90011
- Application / Permit
- 24010-20000-03532
- Plan Check / Job No.
- B24VN14049
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ***ePlan*** New detached ADU at rear of the lot per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g) ; All work per WFPP
- Permit Issued
- Issued on 3/11/2025
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2024 | EDWIN ESPIN |
| Corrections Issued | 8/29/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/19/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 1/30/2025 | REZA HAGHIGHAT |
| Plan Check Approved | 2/9/2025 | REZA HAGHIGHAT |
| Issued | 3/11/2025 | APPLICANT |
| CofO in Progress | 4/15/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/16/2026 | DEROLD HAUFF |
| Permit Finaled | 4/16/2026 | DEROLD HAUFF |
| CofO Issued | 4/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/9/2024 | RIDWAN HARDY |
| Address approval | Cleared | 12/13/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/13/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/5/2025 | JUSTIN BICOL |
Contact Information
| Contractor | Level Up Contractor Inc; Lic. No.: 1053375-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 3/25/2025 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 3/25/2025 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 5/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/14/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Rough | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Rough | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Underground Mechanical | 7/1/2025 | Partial Approval | WAYNE REGESTER |
| Verify Sprinkler Sign Off | 7/1/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 8/4/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 8/4/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 8/4/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 8/4/2025 | Approved | LUIS CASTRO |
| Rough-Elec/Plmb/HVAC | 8/4/2025 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Rough | 8/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/14/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Rough | 8/15/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 9/2/2025 | Approved | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Approved | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | LUIS CASTRO |
| Insulation | 9/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 9/16/2025 | Corrections Issued | RONNIE MEDINA |
| Insulation | 9/19/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 9/26/2025 | Approved | ANTHONY RAMOS |
| Green Building Rough | 9/26/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/26/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/28/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/28/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/28/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/30/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/30/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/5/2026 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 2/5/2026 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/16/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/16/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/18/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/19/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/19/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/10/2026 | Corrections Issued | SABAS ALONSO |
| Final | 4/14/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |