11779 W RIALTO ST 91352

Certificate Information: 11779 W RIALTO ST 91352

Application / Permit
24010-20000-03530
Plan Check / Job No.
B24VN14047
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New Detached ADU
Permit Issued
Issued on 4/23/2025
Issuing Office
Current Status
CofO in Progress on 5/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/21/2024 APPLICANT
Assigned to Plan Check Engineer 8/26/2024 FERNANDO FLORES
Corrections Issued 8/27/2024 FERNANDO FLORES
Applicant returned to address corrections 10/31/2024 GEORGE ALVAREZ
Applicant returned to address corrections 1/30/2025 GEORGE ALVAREZ
Plan Check Approved 2/14/2025 FERNANDO FLORES
Issued 4/23/2025 APPLICANT
CofO in Progress 5/22/2026 JAVIER RAMOS JR

Permit Application Clearance Information

Clean Up Green Up Cleared 10/16/2024 MAYELA VILLA
Address approval Cleared 10/19/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/19/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/21/2024 CARLOS AGUILERA
Construction near power lines Cleared 11/25/2024 RIDWAN HARDY
Construction within easement Cleared 11/25/2024 RIDWAN HARDY
Private sewage disp. approval Cleared 2/10/2025 DAN RYAN EVANGELISTA

Contact Information

Contractor Sire Energy Inc; Lic. No.: 1027415-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Underground Mechanical 4/30/2025 Partial Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 5/9/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/20/2025 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 6/20/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 6/20/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 6/20/2025 Corrections Issued MATTHEW NELSON
MERV13>=Rough 6/20/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 6/20/2025 Approved MATTHEW NELSON
Underground Mechanical 6/20/2025 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 6/20/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 6/26/2025 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Approved MATTHEW NELSON
Green Building Rough 6/26/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 6/26/2025 Approved MATTHEW NELSON
MERV13>=Rough 6/26/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 6/26/2025 Not Ready for Inspection MATTHEW NELSON
Wood Frame 6/26/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/16/2025 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 7/22/2025 Corrections Issued MATTHEW NELSON
Insulation 7/22/2025 Partial Approval MATTHEW NELSON
Shower Pan 7/22/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/19/2025 Partial Approval MATTHEW NELSON
Green Building Rough 8/19/2025 Approved MATTHEW NELSON
Insulation 8/19/2025 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 8/19/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 9/25/2025 Partial Approval MATTHEW NELSON
Drywall Nailing 9/25/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 3/16/2026 Approved JAVIER RAMOS JR
Final 3/16/2026 Partial Inspection JAVIER RAMOS JR
Green Building Final 3/16/2026 Approved JAVIER RAMOS JR
HVAC-Final 3/16/2026 Approved JAVIER RAMOS JR
MERV13>=Final 3/16/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 3/16/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 3/16/2026 Approved JAVIER RAMOS JR
Smoke Detectors 3/16/2026 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/22/2026 Approved JAVIER RAMOS JR
Final 5/22/2026 OK to Issue CofO JAVIER RAMOS JR