11404 W SUNBURST ST 91342

Certificate Information: 11404 W SUNBURST ST 91342

Application / Permit
24010-20000-03524
Plan Check / Job No.
B24VN13972
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New Detached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d) and (g)
Permit Issued
Issued on 10/16/2024
Issuing Office
Current Status
CofO Issued on 7/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2024 APPLICANT
Assigned to Plan Check Engineer 8/23/2024 DAVID CASTILLO
Corrections Issued 8/26/2024 DAVID CASTILLO
Applicant returned to address corrections 9/19/2024 DAVID CASTILLO
Plan Check Approved 10/14/2024 DAVID CASTILLO
Issued 10/16/2024 INTERNET PERMIT
CofO in Progress 7/18/2025 MICHEL ABAJAN
Permit Finaled 7/25/2025 RUBEN SALAS
CofO Issued 7/25/2025 RUBEN SALAS
Permit Finaled 7/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/27/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/28/2024 RYAN CASTRO
Sewer availability Cleared 8/28/2024 RYAN CASTRO
Hold Cleared 8/30/2024 MARIA VENDIVIL
ZA Case Cleared 9/9/2024 NATHAN ROMINE
ZA Case Cleared 9/9/2024 NATHAN ROMINE
Grading Pre-Inspection Cleared 10/14/2024 DAVID CASTILLO
Hold Cleared 12/19/2024 CARMEN MERAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Habibi,, Shayaan; Lic. No.: C94225 10535 WILSHIRE BLVD APT 1602      LOS ANGELES, CA 90024

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/10/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/23/2024 Corrections Issued MICHEL ABAJAN
Deputy Reinf. Concrete 12/24/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 12/30/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 1/27/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/27/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 1/27/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/5/2025 Approved MICHEL ABAJAN
Green Building Rough 2/5/2025 Approved MICHEL ABAJAN
HVAC-Rough 2/5/2025 Approved MICHEL ABAJAN
MERV13>=Rough 2/5/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/5/2025 Approved MICHEL ABAJAN
Insulation 2/24/2025 Approved MICHEL ABAJAN
Drywall Nailing 3/12/2025 Approved MICHEL ABAJAN
Insulation 3/27/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/28/2025 Not Ready for Inspection MICHEL ABAJAN
Final 7/17/2025 OK to Issue CofO MICHEL ABAJAN
Footing/Foundation/Slab 7/17/2025 Approved MICHEL ABAJAN
Green Building Final 7/17/2025 Approved MICHEL ABAJAN
MERV13>=Final 7/17/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 7/17/2025 Approved MICHEL ABAJAN
Smoke Detectors 7/17/2025 Approved MICHEL ABAJAN