9314 N EL DORADO AVE 91352
Certificate Information: 9314 N EL DORADO AVE 91352
- Application / Permit
- 24010-20000-03485
- Plan Check / Job No.
- B24VN13616
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN New detached adu 800 sq ft per wfpp located between 9316 1/2 El Dorado and 9314 1/2 El Dorado. Checked per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13 D fire sprinklers to be provided throughout
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- Current Status
- Issued on 3/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2024 | JOHN MESIAS |
| Corrections Issued | 8/26/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 10/30/2024 | JOHN MESIAS |
| Plan Check Approved | 11/1/2024 | JOHN MESIAS |
| Issued | 3/7/2025 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 8/27/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 9/13/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 9/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 10/13/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2025 | Approved | DAVID ANDERSON |
| Underground Mechanical | 5/8/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 5/14/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | MATTHEW NELSON |
| Sewer | 8/15/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 9/5/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 10/10/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/10/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 10/10/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/15/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/20/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/20/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 10/20/2025 | Approved | MATTHEW NELSON |