1323 N LA BREA AVE 90028

Certificate Information: 1323 N LA BREA AVE 90028

Application / Permit
24010-20000-03466
Plan Check / Job No.
B24VN13468
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW 1-STORY (48'-9" X 38'-11") RETAIL STORE
Permit Issued
Issued on 6/4/2025
Issuing Office
Valley
Current Status
CofO Corrected on 6/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2024 APPLICANT
Assigned to Zoning Architect 8/22/2024 SARHAD GHEVANDIAN
Assigned to Plan Check Engineer 9/5/2024 VAHAN JIVALAGIAN
Corrections Issued 9/8/2024 VAHAN JIVALAGIAN
Disabled Access Plans Picked Up 9/11/2024 APPLICANT
Green Plans Picked Up 9/12/2024 APPLICANT
Quality Review Completed 9/13/2024 OMID HEDAYAT
Building Plans Picked Up 9/19/2024 APPLICANT
Applicant returned to address corrections 2/14/2025 VAHAN JIVALAGIAN
Plan Check Approved 6/4/2025 VAHAN JIVALAGIAN
Issued 6/4/2025 APPLICANT
CofO in Progress 3/20/2026 DAVID BURKHEAD
CofO Issued-Status Void 3/20/2026 ERNESTO CORRAL
Permit Finaled-Status Void 3/20/2026 ERNESTO CORRAL
Re-Activate Permit 3/24/2026 ERNESTO CORRAL
Permit Finaled 6/8/2026 ADAM BURGESS
CofO Corrected 6/8/2026 ADAM BURGESS
Permit Finaled 6/8/2026 ADAM BURGESS

Permit Application Clearance Information

Address approval Cleared 10/30/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 11/4/2024 CHRISTINA BRACO
Sewer availability Cleared 11/4/2024 CHRISTINA BRACO
Green Code Cleared 11/7/2024 MICHAEL AYERS
DAS Clearance Cleared 11/19/2024 VAHAN JIVALAGIAN
Construction near power lines Cleared 12/17/2024 THERESA NGUYEN
Construction within easement Cleared 12/17/2024 THERESA NGUYEN
Hydrant and Access approval Cleared 1/15/2025 RUEL COLE
Historic Resource Verification Cleared 2/26/2025 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 2/26/2025 ELIZABETH GALLARDO
Roof/Waste drainage to street Cleared 4/29/2025 ABEL CASILLAS
Highway dedication Cleared 5/6/2025 ABEL CASILLAS
Miscellaneous Cleared 5/28/2025 RUBEN VASQUEZ
ZI Cleared 5/28/2025 RUBEN VASQUEZ
Zoning Plan Check Cleared 6/2/2025 SARHAD GHEVANDIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/14/2025 Approved DAVID BURKHEAD
Pre-Inspection 7/29/2025 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 8/7/2025 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 8/22/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Partial Approval DAVID BURKHEAD
Green Building Rough 9/4/2025 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/4/2025 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 9/4/2025 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 9/11/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/11/2025 Not Ready for Inspection LARRY ARNICK
Wood Frame 9/11/2025 Partial Approval LARRY ARNICK
Drywall Nailing 9/26/2025 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/26/2025 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 10/22/2025 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 10/22/2025 Partial Approval DAVID BURKHEAD
Wood Frame 10/22/2025 Partial Approval DAVID BURKHEAD
Insulation 10/31/2025 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 10/31/2025 Corrections Issued EDWIN GREGORYONA
Interior/Exterior Lathing 11/7/2025 Partial Approval DAVID BURKHEAD
Drywall Nailing 11/10/2025 Approved DAVID BURKHEAD
Light Gage Steel Frame 11/25/2025 Partial Approval EDWIN GREGORYONA
Final 1/30/2026 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 1/30/2026 Approved DAVID BURKHEAD
Green Building Final 1/30/2026 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 1/30/2026 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 1/30/2026 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/30/2026 Not Ready for Inspection DAVID BURKHEAD
Final 2/25/2026 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 2/25/2026 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Not Ready DAVID BURKHEAD
Verify Sprinkler Sign Off 2/25/2026 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/25/2026 Not Ready for Inspection DAVID BURKHEAD
Final 3/17/2026 Partial Inspection DAVID BURKHEAD
Green Building Final 3/17/2026 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV No Gas DAVID BURKHEAD
Verify Sprinkler Sign Off 3/17/2026 Approved DAVID BURKHEAD
Wood Frame 3/17/2026 Approved DAVID BURKHEAD
Final 3/20/2026 OK to Issue CofO DAVID BURKHEAD