18911 W RINGLING ST 91356

Certificate Information: 18911 W RINGLING ST 91356

Application / Permit
24010-20000-03453
Plan Check / Job No.
B24VN13371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW DET. 13' x 15' PATIO COVER
Permit Issued
Issued on 11/26/2024
Issuing Office
Current Status
CofO Issued on 4/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 SEAN SHAHMIRI
Corrections Issued 8/26/2024 SEAN SHAHMIRI
Quality Review Completed 8/27/2024 STEVEN KIM
Building Plans Picked Up 8/28/2024 APPLICANT
Applicant returned to address corrections 11/26/2024 SEAN SHAHMIRI
Plan Check Approved 11/26/2024 SEAN SHAHMIRI
Issued 11/26/2024 APPLICANT
CofO in Progress 12/31/2025 JOHN KIDWELL
Permit Finaled 4/18/2026 MICHAEL PELHAM
CofO Issued 4/18/2026 MICHAEL PELHAM
Permit Finaled 4/18/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/4/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 9/12/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/17/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 11/13/2024 KURT CORRAL
Grading Pre-Inspection Cleared 11/26/2024 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/30/2024 Corrections Issued JOHN KIDWELL
Sewer 12/30/2024 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 12/30/2024 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Not Ready for Inspection JOHN KIDWELL
Structural Steel Frame 1/17/2025 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Not Ready for Inspection JOHN KIDWELL
Rough-Elec/Plmb/HVAC 2/20/2025 Not Ready for Inspection JOHN KIDWELL
Shower Pan 2/20/2025 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 2/25/2025 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 2/25/2025 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 2/25/2025 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 4/30/2025 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/1/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 12/1/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 12/1/2025 Approved JOHN KIDWELL
PLUMBING-Final 12/1/2025 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 12/1/2025 Approved JOHN KIDWELL
Final 12/12/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Approved JOHN KIDWELL
Service/Power Release 12/12/2025 Approved JOHN KIDWELL
Smoke Detectors 12/12/2025 Approved JOHN KIDWELL
Final 12/18/2025 Corrections Issued JOHN KIDWELL
Final 12/30/2025 OK to Issue CofO JOHN KIDWELL