18911 W RINGLING ST 91356
Certificate Information: 18911 W RINGLING ST 91356
- Application / Permit
- 24010-20000-03451
- Plan Check / Job No.
- B24VN13371
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL INT & EXT WALLS AND KEEP 1 FOOT OF FRONT FOUNDATION & ERECT AN IRR. SHAPED 62' x 78'-4" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- Current Status
- CofO Issued on 4/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | SEAN SHAHMIRI |
| Corrections Issued | 8/26/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 8/27/2024 | STEVEN KIM |
| Building Plans Picked Up | 8/28/2024 | APPLICANT |
| Applicant returned to address corrections | 11/26/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 11/26/2024 | SEAN SHAHMIRI |
| Issued | 11/26/2024 | APPLICANT |
| CofO in Progress | 12/31/2025 | JOHN KIDWELL |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
| CofO Issued | 4/18/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/4/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 9/12/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/17/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 9/20/2024 | ADALBERTO VERA |
| Permit | Cleared | 10/17/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 11/13/2024 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 11/26/2024 | SEAN SHAHMIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/30/2024 | Corrections Issued | JOHN KIDWELL |
| Sewer | 12/30/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Underground Mechanical | 12/30/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 12/31/2024 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 12/31/2024 | Partial Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 1/6/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/6/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/10/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Inspection | JOHN KIDWELL |
| Structural Steel Frame | 1/17/2025 | Partial Inspection | JOHN KIDWELL |
| Pre-Inspection | 2/3/2025 | Partial Inspection | JOHN KIDWELL |
| Deputy Steel/Welding | 2/4/2025 | Partial Approval | JOHN KIDWELL |
| Deck | 2/20/2025 | Partial Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Partial Approval | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 2/20/2025 | Approved | JOHN KIDWELL |
| Shower Pan | 2/20/2025 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/15/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 4/15/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 4/15/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Wood Construction | 4/16/2025 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 4/30/2025 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/1/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 12/1/2025 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 12/1/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 12/1/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 12/1/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 12/1/2025 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 12/12/2025 | Approved | JOHN KIDWELL |
| Final | 12/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 12/12/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 12/12/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 12/12/2025 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 12/12/2025 | Approved | JOHN KIDWELL |
| Final | 12/18/2025 | Corrections Issued | JOHN KIDWELL |
| Final | 12/30/2025 | OK to Issue CofO | JOHN KIDWELL |