5517 N FALLBROOK AVE 91367

Certificate Information: 5517 N FALLBROOK AVE 91367

Application / Permit
24010-20000-03439
Plan Check / Job No.
B24VN13238
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO in Progress on 4/11/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/16/2024 APPLICANT
Assigned to Plan Check Engineer 8/21/2024 GURUNATH NESARAJAH
Corrections Issued 8/22/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 2/6/2025 GURUNATH NESARAJAH
Plan Check Approved 2/26/2025 GIOVANNY CHAVEZ
Issued 5/7/2025 APPLICANT
CofO in Progress 2/12/2026 TROY SANDERS
No Progress 4/11/2026 MICHAEL PELHAM
CofO in Progress 4/11/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 8/27/2024 KEVIN CHUNG
Roof/Waste drainage to street Cleared 8/27/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 8/28/2024 KEVIN CHUNG
Sewer availability Cleared 8/28/2024 KEVIN CHUNG
Grading Pre-Inspection Cleared 10/23/2024 CHARLES POWELL
Construction near power lines Cleared 1/22/2025 RIDWAN HARDY
GPI Written Notices Cleared 2/26/2025 GURUNATH NESARAJAH

Contact Information

Contractor Diamond Financial Management Inc; Lic. No.: 1093438-B       ,
Contractor Fixify Home Improvement; Lic. No.: 1093438-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2025 Partial Approval TROY SANDERS
Footing/Foundation/Slab 6/6/2025 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 6/6/2025 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 6/10/2025 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/12/2025 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 6/12/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Partial Approval TROY SANDERS
Sewer 6/27/2025 Approved TROY SANDERS
PLUMBING-Rough 7/7/2025 Approved TROY SANDERS
ELECTRICAL-Rough 7/14/2025 Not Ready for Inspection TROY SANDERS
Special/Order Compliance 7/14/2025 Partial Approval TROY SANDERS
ELECTRICAL-Rough 7/16/2025 Approved TROY SANDERS
HVAC-Rough 7/16/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 7/18/2025 Approved TROY SANDERS
Green Building Rough 7/18/2025 Approved TROY SANDERS
Interior/Exterior Lathing 7/18/2025 Partial Approval TROY SANDERS
Verify Sprinkler Sign Off 7/18/2025 Approved TROY SANDERS
Wood Frame 7/18/2025 Approved TROY SANDERS
Drywall Nailing 8/5/2025 Approved TROY SANDERS
Interior/Exterior Lathing 8/5/2025 Partial Approval TROY SANDERS
Interior/Exterior Lathing 8/12/2025 Partial Approval TROY SANDERS
Underground Mechanical 9/4/2025 Partial Approval TROY SANDERS
Final 11/4/2025 Corrections Issued ROBERT GOLD
Green Building Final 11/4/2025 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV No Gas ROBERT GOLD
Service/Power Release 11/4/2025 Not Required ROBERT GOLD
Smoke Detectors 11/4/2025 Approved ROBERT GOLD
Final 11/13/2025 Corrections Issued TROY SANDERS
Final 2/11/2026 OK to Issue CofO TROY SANDERS