22450 W DOLOROSA ST 91367
Certificate Information: 22450 W DOLOROSA ST 91367
- Application / Permit
- 24010-20000-03431
- Plan Check / Job No.
- B24VN13128
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT WITH AN ATTACHED PATIO COVER PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 12/7/2024
- Issuing Office
- Current Status
- CofO Issued on 6/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | SARKIS HARABEDIAN |
| Corrections Issued | 8/17/2024 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 12/3/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 12/5/2024 | SARKIS HARABEDIAN |
| Issued | 12/7/2024 | APPLICANT |
| CofO in Progress | 5/30/2025 | TROY SANDERS |
| Permit Finaled | 6/16/2025 | JOHN JANSON |
| CofO Issued | 6/16/2025 | JOHN JANSON |
| Permit Finaled | 6/16/2025 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/18/2024 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 8/18/2024 | SARKIS HARABEDIAN |
| Address approval | Cleared | 8/20/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/22/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 11/25/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 19300 RINALDI ST, P.O. BOX 8401 PORTER RANCH, CA 91327 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/23/2024 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/31/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 2/20/2025 | Approved | TROY SANDERS |
| Green Building Rough | 2/20/2025 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 2/20/2025 | Approved | TROY SANDERS |
| MERV13>=Rough | 2/20/2025 | Approved | TROY SANDERS |
| PLUMBING-Rough | 2/20/2025 | Approved | TROY SANDERS |
| Shower Pan | 2/20/2025 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 2/20/2025 | Approved | TROY SANDERS |
| Insulation | 2/27/2025 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 3/4/2025 | Approved | TROY SANDERS |
| Green Building Rough | 3/4/2025 | Approved | TROY SANDERS |
| Final | 4/21/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 4/21/2025 | Approved | GEVORK IPCHYAN |
| Green Building Final | 4/21/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| MERV13>=Final | 4/21/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Ready | GEVORK IPCHYAN |
| Service/Power Release | 4/21/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Smoke Detectors | 4/21/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Final | 5/8/2025 | Approved | TROY SANDERS |
| Final | 5/8/2025 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 5/8/2025 | Approved | TROY SANDERS |
| MERV13>=Final | 5/8/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/8/2025 | Approved | TROY SANDERS |
| Smoke Detectors | 5/8/2025 | Approved | TROY SANDERS |
| Final | 5/29/2025 | OK to Issue CofO | TROY SANDERS |