11826 W KLING ST 91607

Certificate Information: 11826 W KLING ST 91607

Application / Permit
24010-20000-03425
Plan Check / Job No.
B24VN13055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (161'-11" X 40' IRREGULAR SHAPE) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND PATIO COVERS. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 1/22/2025
Issuing Office
Current Status
CofO Issued on 3/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 VAHAN JIVALAGIAN
Corrections Issued 8/18/2024 VAHAN JIVALAGIAN
Quality Review Completed 8/21/2024 OMID HEDAYAT
Building Plans Picked Up 8/21/2024 APPLICANT
Applicant returned to address corrections 12/18/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 1/7/2025 VAHAN JIVALAGIAN
Applicant returned to address corrections 1/17/2025 VAHAN JIVALAGIAN
Plan Check Approved 1/22/2025 VAHAN JIVALAGIAN
Issued 1/22/2025 APPLICANT
CofO in Progress 2/10/2026 JAVIER RAMOS JR
Permit Finaled 3/19/2026 RUBEN SALAS
CofO Issued 3/19/2026 RUBEN SALAS
Permit Finaled 3/19/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/18/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 9/18/2024 EDGAR ALCARAZ
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 10/16/2024 EDGAR ALCARAZ
Sewer availability Cleared 10/16/2024 EDGAR ALCARAZ
Trees in Parkway Cleared 10/29/2024 ADALBERTO VERA
Permit Cleared 10/30/2024 EDGAR ALCARAZ
Specific Plan Cleared 11/6/2024 CHRISTIAN PEARSON
Hydrant and Access approval Cleared 12/4/2024 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/19/2025 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 3/4/2025 Conditional Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 3/4/2025 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 3/5/2025 Conditional Approval JUAN VALENZUELA
Pre-Inspection 4/9/2025 Partial Inspection JUAN VALENZUELA
Deputy Steel/Welding 4/16/2025 Conditional Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/5/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/7/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 5/7/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 5/12/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/12/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/12/2025 Approved JAVIER RAMOS JR
Sewer 5/12/2025 Approved JAVIER RAMOS JR
Underground Mechanical 5/12/2025 Partial Approval JAVIER RAMOS JR
HVAC-Rough 5/27/2025 Approved JAVIER RAMOS JR
Shower Pan 5/27/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/10/2025 Approved JAVIER RAMOS JR
Green Building Rough 6/10/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/10/2025 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 6/10/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 6/10/2025 Approved JAVIER RAMOS JR
Insulation 6/16/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/16/2025 Approved JAVIER RAMOS JR
Drywall Nailing 6/24/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/16/2026 Corrections Issued JAVIER RAMOS JR
Service/Power Release 1/16/2026 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 1/16/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/27/2026 Approved JAVIER RAMOS JR
Final 1/27/2026 Partial Inspection JAVIER RAMOS JR
Green Building Final 1/27/2026 Approved JAVIER RAMOS JR
HVAC-Final 1/27/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 1/27/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 1/27/2026 Approved JAVIER RAMOS JR
Final 2/9/2026 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 2/9/2026 Approved JAVIER RAMOS JR
MERV13>=Final 2/9/2026 Approved JAVIER RAMOS JR