3718 S ARLINGTON AVE 90018

Certificate Information: 3718 S ARLINGTON AVE 90018

Application / Permit
24010-20000-03379
Plan Check / Job No.
B24VN12800
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'-0" X 31'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 12/12/2024
Issuing Office
Current Status
CofO Issued on 4/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/19/2024 ARTIN ZARUKIAN
Corrections Issued 8/19/2024 ARTIN ZARUKIAN
Building Plans Picked Up 8/22/2024 APPLICANT
Plan Check Approved 12/12/2024 YAQUB MIRZA
Issued 12/12/2024 APPLICANT
CofO in Progress 4/23/2026 LUIS CASTRO
Permit Finaled 4/26/2026 DEROLD HAUFF
CofO Issued 4/26/2026 DEROLD HAUFF
Permit Finaled 4/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 9/4/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/5/2024 JEANIE LAM
Sewer availability Cleared 9/5/2024 JEANIE LAM
HPOZ Cleared 10/9/2024 DANIEL MATA
Historic monument Cleared 10/9/2024 DANIEL MATA
Construction near power lines Cleared 12/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/11/2025 Approved SABAS ALONSO
Underground Mechanical 3/11/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 3/13/2025 Approved SABAS ALONSO
Underground Mechanical 3/13/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 3/25/2025 Not Ready for Inspection SABAS ALONSO
Deputy Drilled-In Anchors 4/9/2025 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Approved SABAS ALONSO
PLUMBING-Rough 4/9/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 4/21/2025 Approved BARRY HACHE
Interior/Exterior Lathing 4/21/2025 Approved BARRY HACHE
PLUMBING-Rough 4/21/2025 Approved BARRY HACHE
Green Building Rough 4/25/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 4/25/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 4/29/2025 Approved SABAS ALONSO
Green Building Rough 4/29/2025 Approved SABAS ALONSO
Insulation 5/2/2025 Approved ANTHONY RAMOS
Drywall Nailing 5/6/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 5/13/2025 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 5/15/2025 Approved REGINA MENDEZ
Final 12/4/2025 Corrections Issued SABAS ALONSO
Green Building Final 12/4/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 12/4/2025 Approved SABAS ALONSO
Final 1/21/2026 Corrections Issued SABAS ALONSO
Service/Power Release 1/21/2026 Not Ready for Inspection SABAS ALONSO
Final 4/21/2026 Conditional Approval OSVALDO PARAMO
Service/Power Release 4/21/2026 Approved OSVALDO PARAMO
ELECTRICAL-Final 4/22/2026 Approved LUIS CASTRO
Final 4/22/2026 OK to Issue CofO LUIS CASTRO
HVAC-Final 4/22/2026 Approved LUIS CASTRO
PLUMBING-Final 4/22/2026 Approved LUIS CASTRO