3718 S ARLINGTON AVE 90018
Certificate Information: 3718 S ARLINGTON AVE 90018
- Application / Permit
- 24010-20000-03379
- Plan Check / Job No.
- B24VN12800
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-0" X 31'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 4/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 8/19/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/22/2024 | APPLICANT |
| Plan Check Approved | 12/12/2024 | YAQUB MIRZA |
| Issued | 12/12/2024 | APPLICANT |
| CofO in Progress | 4/23/2026 | LUIS CASTRO |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
| CofO Issued | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | JEANIE LAM |
| Sewer availability | Cleared | 9/5/2024 | JEANIE LAM |
| HPOZ | Cleared | 10/9/2024 | DANIEL MATA |
| Historic monument | Cleared | 10/9/2024 | DANIEL MATA |
| Construction near power lines | Cleared | 12/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/11/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/11/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/13/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/13/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 3/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 4/9/2025 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/9/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 4/21/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 4/21/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 4/21/2025 | Approved | BARRY HACHE |
| Green Building Rough | 4/25/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 4/25/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/29/2025 | Approved | SABAS ALONSO |
| Insulation | 5/2/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 5/6/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/13/2025 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 5/15/2025 | Approved | REGINA MENDEZ |
| Final | 12/4/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/4/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/4/2025 | Approved | SABAS ALONSO |
| Final | 1/21/2026 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 1/21/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/21/2026 | Conditional Approval | OSVALDO PARAMO |
| Service/Power Release | 4/21/2026 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/22/2026 | Approved | LUIS CASTRO |
| Final | 4/22/2026 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 4/22/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/22/2026 | Approved | LUIS CASTRO |