13103 W DESMOND ST 91331

Certificate Information: 13103 W DESMOND ST 91331

Application / Permit
24010-20000-03377
Plan Check / Job No.
B24VN12770
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 34' X 25' DETACHED ONE STORY ACCESSORY DWELLING UNIT AS PER CA Govt. Code 65852.2(e)(1)(B) and applicable part ofLAMC 12.22 A.33 (c)-(d), (g), ALL WORK PER WFPP
Permit Issued
Issued on 9/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 RARES BODEA
Corrections Issued 8/19/2024 RARES BODEA
Quality Review Completed 8/29/2024 STEVEN KIM
Building Plans Picked Up 8/30/2024 APPLICANT
Plan Check Approved 9/10/2024 RARES BODEA
Issued 9/10/2024 APPLICANT
CofO in Progress 1/10/2025 MICHEL ABAJAN
Permit Finaled 1/28/2025 RUBEN SALAS
CofO Issued 1/28/2025 RUBEN SALAS
Permit Finaled 1/28/2025 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 8/30/2024 JAZMIN ROQUE
Address approval Cleared 9/3/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/3/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 9/3/2024 RYAN CASTRO
Sewer availability Cleared 9/3/2024 RYAN CASTRO

Contact Information

Contractor G Guttierrez Constrcution Inc; Lic. No.: 1110518-B 13614 FELLOWS AVENUE      SYLMAR, CA 91342

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/11/2024 Partial Approval MICHEL ABAJAN
Pre-Inspection 10/11/2024 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 10/18/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 10/18/2024 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 11/4/2024 Partial Inspection MICHEL ABAJAN
MERV13>=Rough 11/4/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 11/12/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/12/2024 Approved MICHEL ABAJAN
Green Building Rough 11/12/2024 Approved MICHEL ABAJAN
HVAC-Rough 11/12/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/12/2024 Approved MICHEL ABAJAN
MERV13>=Rough 11/12/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 11/12/2024 Approved MICHEL ABAJAN
Insulation 11/18/2024 Conditional Approval MICHEL ABAJAN
Drywall Nailing 11/26/2024 Corrections Issued LOUIS ESCOTO
Shower Pan 11/26/2024 Approved LOUIS ESCOTO
Drywall Nailing 12/3/2024 Approved LOUIS ESCOTO
Insulation 12/3/2024 Approved LOUIS ESCOTO
ELECTRICAL-Final 1/8/2025 Approved MICHEL ABAJAN
Final 1/8/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 1/8/2025 Approved MICHEL ABAJAN
Green Building Final 1/8/2025 Approved MICHEL ABAJAN
HVAC-Final 1/8/2025 Approved MICHEL ABAJAN
MERV13>=Final 1/8/2025 Approved MICHEL ABAJAN
PLUMBING-Final 1/8/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/8/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 1/8/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 1/8/2025 Approved MICHEL ABAJAN
Final 1/10/2025 OK to Issue CofO MICHEL ABAJAN