4245 S KENYON AVE 90066

Certificate Information: 4245 S KENYON AVE 90066

Application / Permit
24010-20000-03368
Plan Check / Job No.
B24VN12669
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
11'6"X17'0" RECREATION ROOM WITH A PATIO COVER SEE COMMENTS
Permit Issued
Issued on 9/19/2024
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 MARVEL DELACRUZ
Corrections Issued 8/17/2024 MARVEL DELACRUZ
Quality Review Completed 8/21/2024 OMID HEDAYAT
Building Plans Picked Up 8/29/2024 APPLICANT
Applicant returned to address corrections 9/13/2024 MARVEL DELACRUZ
Plan Check Approved 9/19/2024 MARVEL DELACRUZ
No Progress 9/19/2024 MARVEL DELACRUZ
Plan Check Approved 9/19/2024 MARVEL DELACRUZ
Issued 9/19/2024 APPLICANT
CofO in Progress 6/23/2025 DAVID FEILER
Permit Finaled 6/26/2025 RICHARD STEINBACH
CofO Issued 6/26/2025 RICHARD STEINBACH
Permit Finaled 6/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 8/23/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/27/2024 DINAH GARIN
ZI Cleared 9/3/2024 ROSALINDA MEZA
Hydrant and Access approval Cleared 9/10/2024 GILBERT URREA
Construction near power lines Cleared 9/11/2024 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 9/12/2024 DIANA RENTERIA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/17/2024 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 10/22/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/22/2024 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 10/28/2024 Approved MICHAEL ALLEN
Special/Order Compliance 10/28/2024 Partial Inspection BOBBY KEY
ELECTRICAL-Rough 12/3/2024 Approved MICHAEL ALLEN
HVAC-Rough 12/3/2024 Approved MICHAEL ALLEN
PLUMBING-Rough 12/3/2024 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 12/11/2024 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Approved MICHAEL ALLEN
HVAC-Final 12/11/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/7/2025 Partial Approval MICHAEL ALLEN
Insulation 1/13/2025 Corrections Issued MICHAEL ALLEN
Insulation 1/17/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/17/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/17/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/28/2025 Approved RUBEN RIVAS
Drywall Nailing 5/28/2025 Approved RUBEN RIVAS
Final 5/28/2025 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Required RUBEN RIVAS
Service/Power Release 5/28/2025 Corrections Issued RUBEN RIVAS
Smoke Detectors 5/28/2025 Approved RUBEN RIVAS
Final 6/5/2025 Corrections Issued RUBEN RIVAS
Service/Power Release 6/5/2025 Corrections Issued RUBEN RIVAS
Service/Power Release 6/11/2025 Approved RUBEN RIVAS
Final 6/23/2025 OK to Issue CofO DAVID FEILER