10334 1/2 N ELDORA AVE 91040
Certificate Information: 10334 1/2 N ELDORA AVE 91040
- Application / Permit
- 24010-20000-03366
- Plan Check / Job No.
- B24VN12654
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-6" x 32' DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 8/17/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/21/2024 | APPLICANT |
| Applicant returned to address corrections | 9/6/2024 | MADISON ODELL |
| Applicant returned to address corrections | 9/17/2024 | SEWADA ZADOORIAN MILAGARDI |
| Issued | 9/23/2024 | APPLICANT |
| CofO in Progress | 3/13/2025 | DAVID ANDERSON |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| CofO Issued | 4/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/26/2024 | CHARLES POWELL |
| Address approval | Cleared | 8/28/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 8/28/2024 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 9/23/2024 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/21/2024 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 10/21/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/23/2024 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 10/23/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/30/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/30/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 12/4/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/11/2024 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/11/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/11/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 12/11/2024 | Approved | DAVID ANDERSON |
| Sewer | 12/11/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 12/11/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 12/12/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/12/2024 | Approved | DAVID ANDERSON |
| Insulation | 12/17/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/17/2024 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 12/30/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/2/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 1/2/2025 | Approved | DAVID ANDERSON |
| Final | 3/13/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 3/13/2025 | Approved | DAVID ANDERSON |
| Service/Power Release | 3/13/2025 | Approved | DAVID ANDERSON |
| Smoke Detectors | 3/13/2025 | Approved | DAVID ANDERSON |