4173 N SUNNYSLOPE AVE 91423

Certificate Information: 4173 N SUNNYSLOPE AVE 91423

Application / Permit
24010-20000-03312
Plan Check / Job No.
B24VN12371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 45'4" X 19'1" ONE STORY DETACHED ACCESSORY DWELLING UNIT AS PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/27/2024
Issuing Office
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 RARES BODEA
Corrections Issued 8/19/2024 RARES BODEA
Quality Review Completed 8/22/2024 STEVEN KIM
Building Plans Picked Up 8/23/2024 APPLICANT
Applicant returned to address corrections 11/21/2024 RARES BODEA
Plan Check Approved 11/27/2024 RARES BODEA
Issued 11/27/2024 APPLICANT
CofO in Progress 5/7/2026 MISAEL ESPARZA
Permit Finaled 6/2/2026 RUBEN SALAS
CofO Issued 6/2/2026 RUBEN SALAS
Permit Finaled 6/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/20/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/21/2024 RYAN CASTRO
Sewer availability Cleared 8/21/2024 RYAN CASTRO
Low Impact Development (LID) Cleared 8/26/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/3/2024 RYAN CASTRO
GPI Written Notices Cleared 11/19/2024 RARES BODEA
Grading Pre-Inspection Cleared 11/19/2024 RARES BODEA
Construction near power lines Cleared 11/23/2024 TINA MIRANDA
Construction within easement Cleared 11/23/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/12/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 2/12/2025 Partial Approval MISAEL ESPARZA
Pre-Inspection 2/12/2025 Partial Inspection MISAEL ESPARZA
Underground Mechanical 2/12/2025 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/21/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/14/2025 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 4/25/2025 Approved JAVIER RAMOS JR
HVAC-Rough 5/5/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/5/2025 Approved MISAEL ESPARZA
Shower Pan 5/14/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/13/2025 Conditional Approval MISAEL ESPARZA
Green Building Rough 6/13/2025 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 6/13/2025 Approved MISAEL ESPARZA
Wood Frame 6/13/2025 Approved MISAEL ESPARZA
Insulation 6/23/2025 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 6/23/2025 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 6/26/2025 Approved LOUIS ESCOTO
Insulation 8/28/2025 Approved MISAEL ESPARZA
Drywall Nailing 9/10/2025 Approved MISAEL ESPARZA
Green Building Rough 9/10/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/24/2026 Not Ready for Inspection MICHAEL CORTEZ
Final 3/24/2026 Not Ready for Inspection MICHAEL CORTEZ
Green Building Final 3/24/2026 Not Ready for Inspection MICHAEL CORTEZ
Service/Power Release 3/24/2026 Not Ready for Inspection MICHAEL CORTEZ
Smoke Detectors 3/24/2026 Not Ready for Inspection MICHAEL CORTEZ
ELECTRICAL-Final 4/10/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 4/10/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/15/2026 Approved MISAEL ESPARZA
Pre-Inspection 4/16/2026 Approved MISAEL ESPARZA
HVAC-Final 4/29/2026 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/1/2026 Approved MISAEL ESPARZA
Final 5/1/2026 OK to Issue CofO MISAEL ESPARZA
Green Building Final 5/1/2026 Approved MISAEL ESPARZA
Service/Power Release 5/1/2026 Approved MISAEL ESPARZA
Smoke Detectors 5/1/2026 Approved MISAEL ESPARZA