398-400 N BONHILL ROAD 90049

Certificate Information: 398-400 N BONHILL ROAD 90049

Application / Permit
24010-20000-03286
Plan Check / Job No.
B24VN12244
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 85'9" X 46' TWO STORY SFD W/ HABITABLE BASEMENT AND ATTACHED TWO CAR GARAGE AND ACCESSORY DWELLING UNIT AS PER LAMC 12.22 A.33(c) and (e), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/28/2024
Issuing Office
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 RARES BODEA
Corrections Issued 8/13/2024 RARES BODEA
Quality Review Completed 8/15/2024 STEVEN KIM
Building Plans Picked Up 8/19/2024 APPLICANT
Applicant returned to address corrections 9/26/2024 RARES BODEA
Applicant returned to address corrections 10/10/2024 RARES BODEA
Applicant returned to address corrections 10/22/2024 RARES BODEA
Plan Check Approved 10/28/2024 RARES BODEA
Issued 10/28/2024 APPLICANT
CofO in Progress 3/27/2026 KEVIN SARGSYAN
Permit Finaled 4/3/2026 RICHARD STEINBACH
CofO Issued 4/3/2026 RICHARD STEINBACH
Permit Finaled 4/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development Cleared 9/4/2024 ORVAL HERNANDEZ-MARCI
Trees in Parkway Cleared 9/10/2024 ADALBERTO VERA
Address approval Cleared 9/15/2024 DARIN LAM
BHO/Hillside ordinance Cleared 9/15/2024 DARIN LAM
BHO/Hillside ordinance Cleared 9/15/2024 DARIN LAM
BHO/Hillside ordinance Cleared 9/15/2024 DARIN LAM
BHO/Hillside ordinance Cleared 9/15/2024 DARIN LAM
BHO/Hillside ordinance Cleared 9/15/2024 DARIN LAM
Permit Cleared 9/15/2024 DARIN LAM
Street Frontage Cleared 9/15/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/16/2024 DARIN LAM
Sewer availability Cleared 9/16/2024 DARIN LAM
GPI Written Notices Cleared 9/26/2024 RARES BODEA
Grading Pre-Inspection Cleared 9/26/2024 RARES BODEA
Roof/Waste drainage to street Cleared 10/9/2024 DARIN LAM
Distance to fire station Cleared 10/10/2024 GILBERT URREA
Hydrant and Access approval Cleared 10/10/2024 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/14/2024 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 12/19/2024 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/20/2024 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 1/7/2025 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 1/21/2025 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 1/21/2025 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 1/23/2025 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 1/31/2025 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 3/11/2025 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 3/11/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 3/26/2025 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 4/10/2025 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 4/10/2025 Partial Approval MEL KHACHATOURIAN
Deputy Reinf. Concrete 4/11/2025 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Corrections Issued KEVIN SARGSYAN
Deputy Steel/Welding 4/23/2025 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval TEMISTOCLES CAAL
Deputy Steel/Welding 4/29/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval ARAM AVEDISIAN
Deputy Steel/Welding 5/13/2025 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 6/30/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/30/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 7/1/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 7/10/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 7/10/2025 Approved KEVIN SARGSYAN
PLUMBING-Rough 7/10/2025 Approved KEVIN SARGSYAN
Reinforced Concrete Frame 7/16/2025 Partial Approval RYAN SALAZAR
Insulation 7/28/2025 Partial Approval KEVIN SARGSYAN
Special/Order Compliance 8/11/2025 Partial Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 8/20/2025 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Partial Approval KEVIN SARGSYAN
Shower Pan 8/20/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/27/2025 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 8/27/2025 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 8/27/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/29/2025 Approved KEVIN SARGSYAN
Green Building Rough 8/29/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 8/29/2025 Approved KEVIN SARGSYAN
Insulation 9/4/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/4/2025 Approved KEVIN SARGSYAN
Drywall Nailing 9/5/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/19/2026 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 2/26/2026 Approved KEVIN SARGSYAN
PLUMBING-Final 2/26/2026 Approved KEVIN SARGSYAN
Service/Power Release 3/3/2026 Approved KEVIN SARGSYAN
Smoke Detectors 3/17/2026 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 3/18/2026 Approved KEVIN SARGSYAN
Green Building Final 3/18/2026 Approved KEVIN SARGSYAN
HVAC-Final 3/18/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Approved KEVIN SARGSYAN
Final 3/27/2026 OK to Issue CofO KEVIN SARGSYAN