398-400 N BONHILL ROAD 90049
Certificate Information: 398-400 N BONHILL ROAD 90049
- Application / Permit
- 24010-20000-03286
- Plan Check / Job No.
- B24VN12244
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 85'9" X 46' TWO STORY SFD W/ HABITABLE BASEMENT AND ATTACHED TWO CAR GARAGE AND ACCESSORY DWELLING UNIT AS PER LAMC 12.22 A.33(c) and (e), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/28/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | RARES BODEA |
| Corrections Issued | 8/13/2024 | RARES BODEA |
| Quality Review Completed | 8/15/2024 | STEVEN KIM |
| Building Plans Picked Up | 8/19/2024 | APPLICANT |
| Applicant returned to address corrections | 9/26/2024 | RARES BODEA |
| Applicant returned to address corrections | 10/10/2024 | RARES BODEA |
| Applicant returned to address corrections | 10/22/2024 | RARES BODEA |
| Plan Check Approved | 10/28/2024 | RARES BODEA |
| Issued | 10/28/2024 | APPLICANT |
| CofO in Progress | 3/27/2026 | KEVIN SARGSYAN |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/4/2024 | ORVAL HERNANDEZ-MARCI |
| Trees in Parkway | Cleared | 9/10/2024 | ADALBERTO VERA |
| Address approval | Cleared | 9/15/2024 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 9/15/2024 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 9/15/2024 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 9/15/2024 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 9/15/2024 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 9/15/2024 | DARIN LAM |
| Permit | Cleared | 9/15/2024 | DARIN LAM |
| Street Frontage | Cleared | 9/15/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | DARIN LAM |
| Sewer availability | Cleared | 9/16/2024 | DARIN LAM |
| GPI Written Notices | Cleared | 9/26/2024 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 9/26/2024 | RARES BODEA |
| Roof/Waste drainage to street | Cleared | 10/9/2024 | DARIN LAM |
| Distance to fire station | Cleared | 10/10/2024 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 10/10/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2024 | Partial Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 1/7/2025 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/21/2025 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/21/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 1/23/2025 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/31/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 3/11/2025 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/11/2025 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 4/10/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 4/10/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 4/11/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Steel/Welding | 4/23/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 4/29/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Partial Approval | ARAM AVEDISIAN |
| Deputy Steel/Welding | 5/13/2025 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 6/30/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/30/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/1/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/10/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 7/10/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/10/2025 | Approved | KEVIN SARGSYAN |
| Reinforced Concrete Frame | 7/16/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 7/28/2025 | Partial Approval | KEVIN SARGSYAN |
| Special/Order Compliance | 8/11/2025 | Partial Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/20/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 8/20/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/27/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 8/27/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 8/27/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 8/29/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/29/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 9/4/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/4/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 9/5/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/19/2026 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/26/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 2/26/2026 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 3/3/2026 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 3/17/2026 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/18/2026 | Approved | KEVIN SARGSYAN |
| Green Building Final | 3/18/2026 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 3/18/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 3/27/2026 | OK to Issue CofO | KEVIN SARGSYAN |