22605 W MIRANDA ST 91367
Certificate Information: 22605 W MIRANDA ST 91367
- Application / Permit
- 24010-20000-03284
- Plan Check / Job No.
- B24VN12232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 44'-9" X 23'-6" 1-STORY DETACHED ADU per ordinance
- Permit Issued
- Issued on 10/20/2024
- Issuing Office
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | JOHN MESIAS |
| Corrections Issued | 8/12/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 9/27/2024 | JOHN MESIAS |
| Plan Check Approved | 10/3/2024 | JOHN MESIAS |
| Issued | 10/20/2024 | APPLICANT |
| CofO in Progress | 6/11/2025 | TROY SANDERS |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
| CofO Issued | 7/18/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/9/2024 | CARLOS AGUILERA |
| ZA Case | Cleared | 9/30/2024 | ALEX VELA |
| ZA Case | Cleared | 9/30/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: NA53080 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2024 | Corrections Issued | GEVORK IPCHYAN |
| PLUMBING-Rough | 12/11/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 12/13/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 1/24/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 1/24/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 1/30/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 2/20/2025 | Approved | TROY SANDERS |
| Green Building Rough | 2/20/2025 | Approved | TROY SANDERS |
| HVAC-Rough | 2/20/2025 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | TROY SANDERS |
| Insulation | 2/21/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 2/27/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 2/28/2025 | Approved | TROY SANDERS |
| Underground Mechanical | 4/29/2025 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 5/23/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 6/4/2025 | Approved | TROY SANDERS |
| PLUMBING-Final | 6/4/2025 | Approved | TROY SANDERS |
| Service/Power Release | 6/4/2025 | Approved | TROY SANDERS |
| Final | 6/9/2025 | OK to Issue CofO | TROY SANDERS |
| Footing/Foundation/Slab | 6/9/2025 | Approved | TROY SANDERS |
| HVAC-Final | 6/9/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 6/9/2025 | Approved | TROY SANDERS |
| PLUMBING-Final | 6/10/2025 | Approved | JOHN COLEMAN |