11864 N BORDEN AVE 91340
Certificate Information: 11864 N BORDEN AVE 91340
- Application / Permit
- 24010-20000-03267
- Plan Check / Job No.
- B24VN12128
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 24'8" X 26'1" IRREGULAR SHAPED DETACHED TWO STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22 A.33 (c)-(d), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/1/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | RARES BODEA |
| Corrections Issued | 9/5/2024 | RARES BODEA |
| Quality Review Completed | 9/11/2024 | STEVEN KIM |
| Applicant returned to address corrections | 10/18/2024 | RARES BODEA |
| Plan Check Approved | 10/31/2024 | RARES BODEA |
| Issued | 11/1/2024 | APPLICANT |
| CofO in Progress | 5/14/2025 | MICHEL ABAJAN |
| Permit Finaled | 5/27/2025 | RUBEN SALAS |
| Permit Finaled | 5/27/2025 | RUBEN SALAS |
| CofO Issued | 5/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/26/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/1/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 10/2/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/2/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
| Engineer | Vartanian,, Albert; Lic. No.: NA39989 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/7/2025 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 1/7/2025 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/21/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 2/11/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 2/21/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/21/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/26/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/26/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/26/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/26/2025 | Approved | MICHEL ABAJAN |
| Insulation | 3/3/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/11/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/18/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/13/2025 | Approved | MICHEL ABAJAN |
| Final | 5/13/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 5/13/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/13/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/13/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Smoke Detectors | 5/13/2025 | Approved | MICHEL ABAJAN |