18302 W LINNET ST 91356
Certificate Information: 18302 W LINNET ST 91356
- Application / Permit
- 24010-20000-03259
- Plan Check / Job No.
- B24VN12084
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY 17'-8" x 44'-0" DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) WITH ATTACHED GARAGE PER ENGINEERING
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Valley
- Current Status
- Issued on 1/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | ALFRED RAMIREZ |
| Corrections Issued | 8/10/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 8/15/2024 | STEVEN KIM |
| Building Plans Picked Up | 8/16/2024 | APPLICANT |
| Applicant returned to address corrections | 12/3/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 12/11/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/6/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 1/22/2025 | ALFRED RAMIREZ |
| Issued | 1/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/21/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 8/27/2024 | GERMAN RODRIGUEZ MENDOZA |
| Trees in Parkway | Cleared | 11/12/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 11/14/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 12/5/2024 | ALFRED RAMIREZ |
| Permit | Cleared | 12/5/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2025 | Partial Inspection | JOHN KIDWELL |
| Underground Mechanical | 1/31/2025 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 2/10/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Conditional Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/12/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 3/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 3/12/2025 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | JOHN KIDWELL |
| Green Building Rough | 4/4/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/4/2025 | Partial Approval | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 4/4/2025 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 4/4/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 4/21/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 4/21/2025 | Approved | JOHN KIDWELL |
| Sewer | 5/6/2025 | Approved | MORRIS JACKSON |
| Final | 12/10/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 12/10/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Not Required | JOHN KIDWELL |
| Service/Power Release | 12/10/2025 | Approved | JOHN KIDWELL |
| Smoke Detectors | 12/10/2025 | Approved | JOHN KIDWELL |