23002 W HATTERAS ST 91367
Certificate Information: 23002 W HATTERAS ST 91367
- Application / Permit
- 24010-20000-03232
- Plan Check / Job No.
- B24VN11876
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- PROPOSED NEW 20'X40' DETACHED 2-CAR GARAGE. CONSTRUCTION DESIGN PER ENGINEER. SEE COMMENTS.
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- CofO Issued on 4/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 8/10/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Applicant returned to address corrections | 9/16/2024 | JESSE ARELLANO |
| Plan Check Approved | 9/17/2024 | PINANK PATEL |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 3/25/2026 | TROY SANDERS |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
| CofO Issued | 4/11/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/14/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2024 | CARLOS RAMIREZ |
| GPI Written Notices | Cleared | 9/16/2024 | HAYATO TSUCHIYA |
| Grading Pre-Inspection | Cleared | 9/16/2024 | HAYATO TSUCHIYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/22/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Partial Approval | TROY SANDERS |
| Deputy Wood Construction | 1/24/2025 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | TROY SANDERS |
| Drywall Nailing | 3/10/2026 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 3/10/2026 | Approved | TROY SANDERS |
| Final | 3/10/2026 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 3/10/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/10/2026 | Approved | TROY SANDERS |
| Drywall Nailing | 3/20/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/24/2026 | Approved | TROY SANDERS |
| Final | 3/24/2026 | OK to Issue CofO | TROY SANDERS |
| HVAC-Final | 3/24/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 3/24/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 3/24/2026 | Approved | TROY SANDERS |
| Smoke Detectors | 3/24/2026 | Approved | TROY SANDERS |