5732 N STANSBURY AVE 91401
Certificate Information: 5732 N STANSBURY AVE 91401
- Application / Permit
- 24010-20000-03230
- Plan Check / Job No.
- B24VN11847
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Suppl. permit to renew 13010-20000-01088 at 50% and revise work description to "New Det. 22' X 37' Accessory Dwelling Unit per LAMC 12.22A.33(c) & (d). All work per WFPP. NFPA 13D REQUIRED THROUGHOUT" "COMPLY WITH DEPARTMENT ORDER effective date 04/09/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 8/10/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Applicant returned to address corrections | 10/9/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 11/7/2024 | ANGELICA DAVE |
| Plan Check Approved | 11/8/2024 | ANGELICA MARTINEZ |
| Issued | 11/8/2024 | APPLICANT |
| CofO in Progress | 2/5/2025 | JONATHAN FRANCHINI |
| CofO in Progress | 2/14/2025 | JONATHAN FRANCHINI |
| No Progress | 2/14/2025 | JONATHAN FRANCHINI |
| Permit Finaled | 2/28/2025 | JONATHAN FRANCHINI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Address approval | Cleared | 10/10/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2024 | Corrections Issued | JONATHAN FRANCHINI |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | JONATHAN FRANCHINI |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Approved | JONATHAN FRANCHINI |
| Green Building Rough | 11/19/2024 | Partial Approval | JONATHAN FRANCHINI |
| Interior/Exterior Lathing | 11/25/2024 | Approved | PTOLEMY HILL |
| PLUMBING-Rough | 11/25/2024 | Approved | PTOLEMY HILL |
| Shower Pan | 11/25/2024 | Approved | PTOLEMY HILL |
| Drywall Nailing | 12/3/2024 | Approved | JONATHAN FRANCHINI |
| ELECTRICAL-Rough | 12/3/2024 | Approved | JONATHAN FRANCHINI |
| Green Building Rough | 12/3/2024 | Approved | JONATHAN FRANCHINI |
| HVAC-Rough | 12/3/2024 | Approved | JONATHAN FRANCHINI |
| Gas Test | 12/5/2024 | Approved | JONATHAN FRANCHINI |
| Final | 12/16/2024 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Green Building Final | 12/16/2024 | Approved | JONATHAN FRANCHINI |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Approved | JONATHAN FRANCHINI |
| Smoke Detectors | 12/16/2024 | Approved | JONATHAN FRANCHINI |
| Final | 12/20/2024 | Partial Approval | JONATHAN FRANCHINI |
| ELECTRICAL-Final | 2/4/2025 | Approved | JONATHAN FRANCHINI |
| Final | 2/4/2025 | OK to Issue CofO | JONATHAN FRANCHINI |
| HVAC-Final | 2/4/2025 | Approved | JONATHAN FRANCHINI |
| PLUMBING-Final | 2/4/2025 | Approved | JONATHAN FRANCHINI |
| Service/Power Release | 2/7/2025 | Approved | JONATHAN FRANCHINI |