1135 1/2 E 21ST ST 90011

Certificate Information: 1135 1/2 E 21ST ST 90011

Application / Permit
24010-20000-03194
Plan Check / Job No.
B24VN11440
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-story detached ADU (1050 SF) per LAMC 12.22 A.33(b)(1).
Permit Issued
Issued on 8/4/2025
Issuing Office
Current Status
CofO Issued on 5/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/7/2024 KELVIN CHUONG
Corrections Issued 8/8/2024 KELVIN CHUONG
Applicant returned to address corrections 7/21/2025 DANIEL SMILEY
Plan Check Approved 7/31/2025 DANIEL SMILEY
Issued 8/4/2025 APPLICANT
CofO in Progress 5/13/2026 ALEJANDRO DE ARTOLA
CofO Issued 5/16/2026 DEROLD HAUFF
Permit Finaled 5/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/15/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/15/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/15/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/15/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/24/2025 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 9/24/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/29/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Approved LUIS CASTRO
HVAC-Rough 10/20/2025 Approved LUIS CASTRO
PLUMBING-Rough 10/20/2025 Approved LUIS CASTRO
Underground Mechanical 10/20/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 11/20/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 11/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 11/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/1/2025 Approved JOHN QUINTANILLA
Green Building Rough 12/1/2025 Approved JOHN QUINTANILLA
Insulation 12/1/2025 Conditional Approval JOHN QUINTANILLA
Shower Pan 12/1/2025 Approved JOHN QUINTANILLA
Drywall Nailing 12/3/2025 Approved ANTHONY RAMOS
Insulation 12/3/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 12/3/2025 Partial Approval ANTHONY RAMOS
Interior/Exterior Lathing 12/4/2025 Approved ALEX COLIN
Sewer 1/6/2026 Not Ready for Inspection BARRY HACHE
Sewer 1/16/2026 Approved ALEJANDRO DE ARTOLA
Service/Power Release 1/22/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/26/2026 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 1/26/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/29/2026 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 1/29/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/11/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/11/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/11/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/12/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/12/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/12/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/13/2026 Approved ALEJANDRO DE ARTOLA
Final 5/13/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 5/13/2026 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 5/13/2026 Approved ALEJANDRO DE ARTOLA