10153-10155 N SWINTON AVE 91343
Certificate Information: 10153-10155 N SWINTON AVE 91343
- Application / Permit
- 24010-20000-03188
- Plan Check / Job No.
- B24VN11362
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (54'-6" X 23'-6") SINGLE FAMILY DWELLING PER SB9 TWO-UNIT DEVELOPMENT CA GOVT. CODE 65852.21 WITH AN ATTACHED COVERED PATIO AND ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 8/21/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 8/22/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 8/23/2024 | APPLICANT |
| Plan Check Approved | 11/22/2024 | VAHAN JIVALAGIAN |
| Issued | 12/6/2024 | APPLICANT |
| CofO in Progress | 10/30/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
| CofO Issued | 11/18/2025 | RUBEN SALAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 8/29/2024 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 9/5/2024 | GERMAN RODRIGUEZ MENDO |
| Miscellaneous | Cleared | 11/1/2024 | NATHAN ROMINE |
| Senate Bill 9 | Cleared | 11/1/2024 | NATHAN ROMINE |
| Construction within easement | Cleared | 11/3/2024 | TINA MIRANDA |
| Hydrant and Access approval | Cleared | 11/14/2024 | PATRICK PEREZ |
| GPI Written Notices | Cleared | 11/22/2024 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/16/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/23/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | ROBERT GOLD |
| Underground Mechanical | 2/24/2025 | Not Ready for Inspection | ROBERT GOLD |
| Pre-Inspection | 4/9/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Sewer | 4/24/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/1/2025 | OK to Expire Permit | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/14/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/20/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 5/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/20/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 5/20/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 5/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 5/20/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 6/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 6/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 6/27/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 6/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 6/27/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/1/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 7/1/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 9/25/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 9/25/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 9/25/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | RAUL OLAGI |
| Drywall Nailing | 9/29/2025 | Approved | RAUL OLAGI |
| Final | 9/29/2025 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/29/2025 | Approved | RAUL OLAGI |
| Green Building Rough | 9/29/2025 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Not Required | RAUL OLAGI |
| Service/Power Release | 9/29/2025 | Not Ready for Inspection | RAUL OLAGI |
| Smoke Detectors | 9/29/2025 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 9/29/2025 | Approved | RAUL OLAGI |
| Final | 10/6/2025 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 10/6/2025 | No Access for Inspection | RAUL OLAGI |
| Final | 10/29/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 10/29/2025 | Approved | CHRISTOPHER ROJAS |