5955 N JUMILLA AVE 91367
Certificate Information: 5955 N JUMILLA AVE 91367
- Application / Permit
- 24010-20000-03182
- Plan Check / Job No.
- B24VN11325
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW 41' X 77' ONE STORY STORAGE BUILDING WITH ATTIC
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Current Status
- CofO Issued on 2/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | SELLA BENYAMIN |
| Corrections Issued | 8/6/2024 | SELLA BENYAMIN |
| Quality Review Completed | 8/9/2024 | STEVEN KIM |
| Building Plans Picked Up | 8/12/2024 | APPLICANT |
| Plan Check Approved | 9/19/2024 | SELLA BENYAMIN |
| Issued | 9/26/2024 | APPLICANT |
| CofO in Progress | 12/15/2025 | JON MCHUGH |
| No Progress | 1/14/2026 | JON MCHUGH |
| CofO in Progress | 1/14/2026 | JON MCHUGH |
| Permit Finaled | 2/18/2026 | JOHN JANSON |
| CofO Issued | 2/18/2026 | JOHN JANSON |
| Permit Finaled | 2/18/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/16/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Corrections Issued | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Not Ready for Inspection | JON MCHUGH |
| Pre-Inspection | 12/2/2024 | Partial Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 12/11/2024 | Approved | JON MCHUGH |
| Special/Order Compliance | 12/11/2024 | Corrections Issued | JON MCHUGH |
| Underground Mechanical | 12/11/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 7/16/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Corrections Issued | JON MCHUGH |
| Deputy Steel/Welding | 8/6/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/22/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 8/22/2025 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 8/22/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/22/2025 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 8/22/2025 | Corrections Issued | JON MCHUGH |
| Verify Sprinkler Sign Off | 8/22/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 10/1/2025 | Approved | JON MCHUGH |
| Insulation | 10/1/2025 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 10/1/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 10/7/2025 | Approved | JON MCHUGH |
| Final | 12/10/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 12/10/2025 | Approved | MORRIS JACKSON |
| Green Building Final | 12/10/2025 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 12/10/2025 | Partial Inspection | MORRIS JACKSON |
| Smoke Detectors | 12/10/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 12/12/2025 | Approved | JON MCHUGH |
| Final | 12/12/2025 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 12/12/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 12/12/2025 | Approved | JON MCHUGH |