23906 W GILMORE ST 91307
Certificate Information: 23906 W GILMORE ST 91307
- Application / Permit
- 24010-20000-03176
- Plan Check / Job No.
- B24VN11313
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- PROPOSED NEW 15'X15' DETACHED PATIO COVER PER ENGR DESIGN.
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2024 | KAMYAR EMAMI |
| Corrections Issued | 7/30/2024 | KAMYAR EMAMI |
| Plan Check Approved | 8/1/2024 | HAYATO TSUCHIYA |
| Issued | 8/1/2024 | APPLICANT |
| CofO in Progress | 1/23/2025 | GEVORK IPCHYAN |
| Permit Finaled | 1/27/2025 | JOHN JANSON |
| CofO Issued | 1/27/2025 | JOHN JANSON |
| Permit Finaled | 1/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/31/2024 | EDGAR PASCUA |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/31/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Contractor | We Build Green Inc; Lic. No.: 1073455-B | 24306 GILMORE WEST HILLS, CA 91307 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | No Access for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 8/28/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 8/29/2024 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 8/29/2024 | Approved | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 8/29/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 9/4/2024 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 9/16/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | GEVORK IPCHYAN |
| Final | 1/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 1/14/2025 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | GEVORK IPCHYAN |
| Service/Power Release | 1/14/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Smoke Detectors | 1/14/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 1/17/2025 | Approved | GEVORK IPCHYAN |
| Final | 1/17/2025 | OK to Issue CofO | GEVORK IPCHYAN |
| HVAC-Final | 1/17/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 1/17/2025 | Approved | GEVORK IPCHYAN |
| Service/Power Release | 1/17/2025 | Approved | GEVORK IPCHYAN |