13260 W TERRA BELLA ST 91331
Certificate Information: 13260 W TERRA BELLA ST 91331
- Application / Permit
- 24010-20000-03161
- Plan Check / Job No.
- B24VN11225
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN-(N) DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(2)
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- CofO Issued on 7/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2024 | SERGIO MUNIZ |
| Corrections Issued | 8/1/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/8/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 7/9/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 8/29/2025 | APPLICANT |
| CofO in Progress | 6/2/2026 | MICHEL ABAJAN |
| Permit Finaled | 7/8/2026 | RUBEN SALAS |
| CofO Issued | 7/8/2026 | RUBEN SALAS |
| Permit Finaled | 7/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/15/2024 | CARLOS AGUILERA |
| Clean Up Green Up | Cleared | 8/20/2024 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/1/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| METHANE-Barrier | 10/3/2025 | Approved | KEVIN BERBERYAN |
| METHANE-Subgrade | 10/3/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 10/16/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 10/28/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Wood Frame | 10/28/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 12/15/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/13/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/13/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 1/13/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/13/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 1/13/2026 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 1/13/2026 | Approved | MICHEL ABAJAN |
| Insulation | 1/20/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/20/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/3/2026 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/3/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/11/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 4/27/2026 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 4/27/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 4/27/2026 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/8/2026 | Approved | MICHEL ABAJAN |
| Final | 5/8/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/8/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/8/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/8/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 5/8/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 5/8/2026 | Approved | MICHEL ABAJAN |
| Final | 5/18/2026 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 5/18/2026 | Approved | MICHEL ABAJAN |