9970 N HADDON AVE 91331

Certificate Information: 9970 N HADDON AVE 91331

Application / Permit
24010-20000-03155
Plan Check / Job No.
B24VN11191
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 2 BED 1 BATH 768 SF ADU AT THE REAR SIDE OF THE PROPERTY LAMC 12.22 A.33(c) AND (d). WORK PER WFPP
Permit Issued
Issued on 11/8/2024
Issuing Office
Current Status
Issued on 11/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/3/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 NGHI SU
Corrections Issued 8/9/2024 NGHI SU
Applicant returned to address corrections 10/10/2024 NGHI SU
Applicant returned to address corrections 10/25/2024 NGHI SU
Plan Check Approved 10/31/2024 NGHI SU
Issued 11/8/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/22/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/22/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/22/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/23/2024 LEE GUILBEAUX
Sewer availability Cleared 10/23/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/9/2025 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 2/24/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 2/24/2025 Not Ready for Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/12/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 3/12/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/20/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 5/23/2025 Approved MICHEL ABAJAN
HVAC-Rough 5/23/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 5/23/2025 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 6/6/2025 Conditional Approval KEVIN BERBERYAN
Shower Pan 6/6/2025 Approved KEVIN BERBERYAN
Wood Frame 6/6/2025 Approved KEVIN BERBERYAN
Insulation 7/14/2025 Approved MICHEL ABAJAN
Drywall Nailing 7/23/2025 Approved MICHEL ABAJAN
Sewer 9/17/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/30/2025 Approved KEVIN BERBERYAN
Final 10/30/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 10/30/2025 Approved KEVIN BERBERYAN
Green Building Rough 10/30/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 10/30/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 10/30/2025 Not Ready for Inspection KEVIN BERBERYAN