10556 W PENROSE ST 91352

Certificate Information: 10556 W PENROSE ST 91352

Application / Permit
24010-20000-03153
Plan Check / Job No.
B24VN11179
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ePlan: New 25'x40' RV Garage Approved per DIR-2024-7735-SPPC.
Permit Issued
Issued on 12/23/2025
Issuing Office
Current Status
CofO in Progress on 5/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 ALEXANDER JOO
Corrections Issued 8/5/2024 ALEXANDER JOO
Applicant returned to address corrections 12/4/2025 GEORGE ALVAREZ
Plan Check Approved 12/23/2025 JOSE VELAZQUEZ
Issued 12/23/2025 APPLICANT
CofO in Progress 5/30/2026 DAVID ANDERSON

Permit Application Clearance Information

Miscellaneous Cleared 9/9/2024 ALEX VELA
Miscellaneous Cleared 9/9/2024 ALEX VELA
ZA Case Cleared 9/9/2024 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 8/26/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/26/2025 SAFA JAVANMARDI
Specific Plan Cleared 8/29/2025 STEVEN WECHSLER
GPI Written Notices Cleared 12/4/2025 ALEXANDER JOO
Grading Pre-Inspection Cleared 12/4/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: NA69935       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2026 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 3/31/2026 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 4/3/2026 Approved DAVID ANDERSON
ELECTRICAL-Rough 4/28/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Partial Approval DAVID ANDERSON
Deputy Wood Construction 5/4/2026 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/8/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/19/2026 Approved DAVID ANDERSON
Final 5/19/2026 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Not Required DAVID ANDERSON
Service/Power Release 5/19/2026 Approved DAVID ANDERSON
Smoke Detectors 5/19/2026 Approved DAVID ANDERSON