8532 N PENFIELD AVE 91306

Certificate Information: 8532 N PENFIELD AVE 91306

Application / Permit
24010-20000-03144
Plan Check / Job No.
B24VN11144
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 30'-5" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/4/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 SELLA BENYAMIN
Corrections Issued 8/20/2024 SELLA BENYAMIN
Quality Review Completed 8/21/2024 STEVEN KIM
Building Plans Picked Up 8/22/2024 APPLICANT
Plan Check Approved 2/4/2025 SELLA BENYAMIN
Issued 2/4/2025 APPLICANT
CofO in Progress 9/2/2025 CHRIS CHRISTENSEN
Permit Finaled 9/17/2025 JOHN JANSON
CofO Issued 9/17/2025 JOHN JANSON
Permit Finaled 9/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/23/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/23/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/23/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/23/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 2/4/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/17/2025 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 3/24/2025 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 4/10/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 4/29/2025 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/1/2025 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/19/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/19/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 5/19/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/19/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/19/2025 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 5/19/2025 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 5/19/2025 Approved CHRIS CHRISTENSEN
Insulation 6/3/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/3/2025 Approved CHRIS CHRISTENSEN
Shower Pan 6/3/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 6/10/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 8/29/2025 Approved CHRIS CHRISTENSEN
Final 8/29/2025 OK to Issue CofO CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/29/2025 Approved CHRIS CHRISTENSEN
Green Building Final 8/29/2025 Approved CHRIS CHRISTENSEN
HVAC-Final 8/29/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 8/29/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 8/29/2025 Approved CHRIS CHRISTENSEN
Smoke Detectors 8/29/2025 Approved CHRIS CHRISTENSEN