11858 N FELLOWS AVE 91340
Certificate Information: 11858 N FELLOWS AVE 91340
- Application / Permit
- 24010-20000-03132
- Plan Check / Job No.
- B24VN11096
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW 1-STORY IRREGULAR SHAPED 67'-1" x 50'-0" S.F.D. WITH ATTACHED COVERED PATIOS AT FRONT AND REAR AND 2-CAR GARAGE/STORAGE PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 12/9/2024
- Issuing Office
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | ALFRED RAMIREZ |
| Corrections Issued | 8/22/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 8/23/2024 | STEVEN KIM |
| Applicant returned to address corrections | 10/2/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 11/15/2024 | ALFRED RAMIREZ |
| Issued | 12/9/2024 | APPLICANT |
| CofO in Progress | 1/23/2026 | MICHEL ABAJAN |
| Permit Finaled | 2/10/2026 | RUBEN SALAS |
| CofO Issued | 2/10/2026 | RUBEN SALAS |
| Permit Finaled | 2/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/1/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/3/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 11/6/2024 | JERRY KAO |
Contact Information
| Contractor | Whitehouse Builders; Lic. No.: 956410-B | , |
| Contractor | Whitehouse Construction Inc; Lic. No.: 956410-B | , |
| Engineer | Clayton,, Andrew; Lic. No.: NA85452 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/27/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/24/2025 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 6/25/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/19/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 9/19/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/19/2025 | Partial Approval | KEVIN BERBERYAN |
| Wood Frame | 9/19/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/26/2025 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 10/1/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 10/7/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/7/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/23/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 12/22/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/22/2025 | Approved | MICHEL ABAJAN |
| Final | 12/22/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/22/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/22/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/22/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 12/22/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 12/22/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/22/2025 | Approved | MICHEL ABAJAN |
| Final | 1/20/2026 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 1/20/2026 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 1/20/2026 | Partial Inspection | DAVID MATSON |