4246 N FARMDALE AVE 91604

Certificate Information: 4246 N FARMDALE AVE 91604

Application / Permit
24010-20000-03128
Plan Check / Job No.
B24VN11084
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
EPLAN: NEW 2-CAR 19'-3" x 21'-3" DETACHED GARAGE PER ENGINEERING. SEE COMMENTS
Permit Issued
Issued on 11/17/2024
Issuing Office
Current Status
CofO Issued on 12/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 ALFRED RAMIREZ
Corrections Issued 8/6/2024 ALFRED RAMIREZ
Quality Review Completed 8/13/2024 STEVEN KIM
Applicant returned to address corrections 9/4/2024 ALFRED RAMIREZ
Applicant returned to address corrections 10/2/2024 ALFRED RAMIREZ
Plan Check Approved 11/13/2024 ALFRED RAMIREZ
No Progress 11/15/2024 ALFRED RAMIREZ
Plan Check Approved 11/15/2024 ALFRED RAMIREZ
No Progress 11/15/2024 ALFRED RAMIREZ
Plan Check Approved 11/15/2024 ALFRED RAMIREZ
No Progress 11/15/2024 ALFRED RAMIREZ
Plan Check Approved 11/15/2024 ALFRED RAMIREZ
Issued 11/17/2024 APPLICANT
CofO in Progress 4/16/2025 JAVIER RAMOS JR
Permit Finaled 12/16/2025 RUBEN SALAS
CofO Issued 12/16/2025 RUBEN SALAS
Permit Finaled 12/16/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 8/13/2024 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 8/14/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 8/20/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/18/2024 CARLOS RAMIREZ

Contact Information

Architect Perella,, Ryan Adam; Lic. No.: NA30833       ,
Contractor Owner-Builder       ,
Engineer Sayah,, Daniel H; Lic. No.: NA67905       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/21/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/14/2025 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 3/10/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/10/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/20/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/21/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 4/7/2025 Approved JAVIER RAMOS JR
Final 4/7/2025 Corrections Issued JAVIER RAMOS JR
Smoke Detectors 4/7/2025 Approved JAVIER RAMOS JR
Final 4/16/2025 OK to Issue CofO JAVIER RAMOS JR