16432 W HALSTED ST 91343

Certificate Information: 16432 W HALSTED ST 91343

Application / Permit
24010-20000-03118
Plan Check / Job No.
B24VN11007
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 2-story ADU at rear of the lot per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 REZA HAGHIGHAT
Corrections Issued 8/17/2024 REZA HAGHIGHAT
Quality Review Completed 8/24/2024 KAVIAN REFAHI
Applicant returned to address corrections 1/9/2025 REZA HAGHIGHAT
Applicant returned to address corrections 1/21/2025 REZA HAGHIGHAT
Plan Check Approved 2/18/2025 REZA HAGHIGHAT
Issued 2/19/2025 APPLICANT
CofO in Progress 9/5/2025 GAREN HAYRAPETYAN
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/22/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/22/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/22/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/22/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/22/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 10/22/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/22/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/22/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/22/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 10/28/2024 CHARLES POWELL
Construction near power lines Cleared 12/20/2024 GEVORK KARAPETYAN
GPI Written Notices Cleared 1/9/2025 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/24/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/24/2025 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/1/2025 Approved MISAEL ESPARZA
Footing/Foundation/Slab 4/1/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval GAREN HAYRAPETYAN
Deputy Wood Construction 4/24/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 5/7/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/7/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 5/8/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval SALVADOR MARTINEZ
Sewer 5/8/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 5/12/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 5/12/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 5/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/14/2025 Approved JENNIFER RABUCHIN
Sewer 5/14/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/16/2025 Corrections Issued SALVADOR MARTINEZ
Verify Sprinkler Sign Off 5/16/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 5/28/2025 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 5/28/2025 Corrections Issued MISAEL ESPARZA
Underground Mechanical 5/28/2025 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 6/3/2025 Partial Approval SALVADOR MARTINEZ
Service/Power Release 6/3/2025 Not Ready for Inspection SALVADOR MARTINEZ
Shower Pan 6/3/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/9/2025 Conditional Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 6/9/2025 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 6/12/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 6/18/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/18/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 6/27/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/21/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/21/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/21/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/21/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 7/28/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 7/28/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/28/2025 Corrections Issued JENNIFER RABUCHIN
Final 8/25/2025 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 8/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 8/25/2025 Approved GAREN HAYRAPETYAN
Final 9/4/2025 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 9/4/2025 Approved GAREN HAYRAPETYAN