7629 N BEN AVE 91605
Certificate Information: 7629 N BEN AVE 91605
- Application / Permit
- 24010-20000-03114
- Plan Check / Job No.
- B24VN10977
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 73' X 35' ONE STORY SINGLE FAMILY DWELLING WITH ATTACHED 18' X 18' CARPORT; EQUIPPED WITH NPFA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | SELLA BENYAMIN |
| Corrections Issued | 8/8/2024 | SELLA BENYAMIN |
| Quality Review Completed | 8/9/2024 | STEVEN KIM |
| Building Plans Picked Up | 8/12/2024 | APPLICANT |
| Applicant returned to address corrections | 10/10/2024 | SELLA BENYAMIN |
| Plan Check Approved | 11/26/2024 | SELLA BENYAMIN |
| Issued | 11/26/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | MATTHEW NELSON |
| Permit Finaled | 9/16/2025 | RUBEN SALAS |
| CofO Issued | 9/16/2025 | RUBEN SALAS |
| Permit Finaled | 9/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/29/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 8/29/2024 | DORIAN AGUILAR |
| Sewer availability | Cleared | 8/29/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 11/12/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/19/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 12/23/2024 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 12/30/2024 | Approved | MATTHEW NELSON |
| Deputy Other (see comments) | 1/2/2025 | Conditional Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 1/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 1/3/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/3/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/24/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/24/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/24/2025 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 2/24/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 2/24/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/7/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/11/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 3/11/2025 | Approved | MATTHEW NELSON |
| Insulation | 3/13/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 3/18/2025 | Conditional Approval | LOUIS ESCOTO |
| Insulation | 3/20/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 3/26/2025 | Corrections Issued | MATTHEW NELSON |
| Shower Pan | 3/28/2025 | Approved | MATTHEW NELSON |
| Sewer | 5/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 5/23/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 6/26/2025 | No Access for Inspection | MATTHEW NELSON |
| Pre-Inspection | 6/26/2025 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/11/2025 | Partial Approval | MATTHEW NELSON |
| Final | 8/11/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 8/11/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/11/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 8/11/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 8/11/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/11/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/21/2025 | Approved | MATTHEW NELSON |
| Final | 8/21/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 8/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 8/26/2025 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 8/26/2025 | Approved | MATTHEW NELSON |