5643 N RAMARA AVE 91367

Certificate Information: 5643 N RAMARA AVE 91367

Application / Permit
24010-20000-03112
Plan Check / Job No.
B24VN10973
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ePlan: New Detached Recreational Room
Permit Issued
Issued on 11/4/2024
Issuing Office
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/29/2024 AMY GUEVARRA
Corrections Issued 8/6/2024 AMY GUEVARRA
Applicant returned to address corrections 10/24/2024 AMY GUEVARRA
Plan Check Approved 10/28/2024 AMY GUEVARRA
Issued 11/4/2024 APPLICANT
CofO in Progress 5/2/2025 TROY SANDERS
Permit Finaled 5/29/2025 JOHN JANSON
CofO Issued 5/29/2025 JOHN JANSON
Permit Finaled 5/29/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/7/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/7/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/9/2024 LEE GUILBEAUX
Grading Pre-Inspection Cleared 10/27/2024 AMY GUEVARRA

Contact Information

Contractor Owner-Builder       ,
Engineer Sparks,, David Michael; Lic. No.: NA65739       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/6/2024 Approved GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 12/19/2024 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 12/19/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 1/16/2025 Partial Approval GEVORK IPCHYAN
Deputy Drilled-In Anchors 1/21/2025 Conditional Approval TROY SANDERS
BUILDING-Rough-Frame 1/23/2025 Approved GEVORK IPCHYAN
Insulation 1/23/2025 Approved GEVORK IPCHYAN
Underground Mechanical 1/23/2025 Approved GEVORK IPCHYAN
Verify Sprinkler Sign Off 1/23/2025 Approved GEVORK IPCHYAN
Drywall Nailing 1/27/2025 Approved GEVORK IPCHYAN
Final 2/13/2025 Partial Approval GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved GEVORK IPCHYAN
Service/Power Release 2/13/2025 Approved GEVORK IPCHYAN
Smoke Detectors 2/13/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 5/1/2025 Approved TROY SANDERS
Final 5/1/2025 OK to Issue CofO TROY SANDERS