13641 W OTTOMAN ST 91331
Certificate Information: 13641 W OTTOMAN ST 91331
- Application / Permit
- 24010-20000-03072
- Plan Check / Job No.
- B24VN10705
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW DETACHED 1 STORY 500 SF ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/17/2025
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 7/30/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/28/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/3/2024 | LUISANGEL VALENZUELA |
| Issued | 2/17/2025 | APPLICANT |
| CofO in Progress | 7/29/2025 | VINCENT HANLEY |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
| CofO Issued | 8/19/2025 | RUBEN SALAS |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2024 | KENIA CASTILLO |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2024 | KENIA CASTILLO |
| Sewer availability | Cleared | 8/12/2024 | KENIA CASTILLO |
| Construction near power lines | Cleared | 11/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/18/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/18/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/18/2025 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/24/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/24/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/20/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/20/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 5/20/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/29/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/29/2025 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 5/29/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/9/2025 | Approved | VINCENT HANLEY |
| Insulation | 6/9/2025 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/9/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/13/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 7/22/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/22/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/22/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/22/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 7/22/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 7/22/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/28/2025 | Approved | VINCENT HANLEY |
| Final | 7/28/2025 | OK to Issue CofO | VINCENT HANLEY |