7414 N CLEON AVE 91352

Certificate Information: 7414 N CLEON AVE 91352

Application / Permit
24010-20000-03034
Plan Check / Job No.
B24VN10382
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached Accessory Dwelling Unit at rear of lot per Ordinance . Work per wood frame prescriptive provisions .
Permit Issued
Issued on 8/12/2024
Issuing Office
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2024 APPLICANT
Assigned to Plan Check Engineer 7/29/2024 TSE MING HUANG
Corrections Issued 7/30/2024 TSE MING HUANG
Plan Check Approved 8/10/2024 GEORGE ALVAREZ
Issued 8/12/2024 APPLICANT
CofO in Progress 8/4/2025 JOSE AVILA
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 8/1/2024 WALTER RAMIREZ
Construction within easement Cleared 8/1/2024 WALTER RAMIREZ
Address approval Cleared 8/5/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 8/5/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 8/6/2024 CARLOS RAMIREZ
Sewer availability Cleared 8/6/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/22/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/22/2024 Partial Approval JOSE AVILA
Pre-Inspection 10/22/2024 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/31/2024 Approved JOSE AVILA
Footing/Foundation/Slab 11/4/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 12/13/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Corrections Issued JOSE AVILA
HVAC-Rough 1/13/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 1/22/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 1/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/13/2025 Approved JOSE AVILA
Shower Pan 3/14/2025 No Access for Inspection MICHAEL CORTEZ
Shower Pan 3/17/2025 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 3/24/2025 Approved JOSE AVILA
Shower Pan 3/24/2025 Approved JOSE AVILA
Sewer 4/30/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/22/2025 Corrections Issued JOSE AVILA
Final 6/4/2025 Corrections Issued JOSE AVILA
Service/Power Release 6/4/2025 Approved JOSE AVILA
Smoke Detectors 6/4/2025 Approved JOSE AVILA
Final 8/1/2025 OK to Issue CofO JOSE AVILA