7414 N CLEON AVE 91352
Certificate Information: 7414 N CLEON AVE 91352
- Application / Permit
- 24010-20000-03034
- Plan Check / Job No.
- B24VN10382
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached Accessory Dwelling Unit at rear of lot per Ordinance . Work per wood frame prescriptive provisions .
- Permit Issued
- Issued on 8/12/2024
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2024 | TSE MING HUANG |
| Corrections Issued | 7/30/2024 | TSE MING HUANG |
| Plan Check Approved | 8/10/2024 | GEORGE ALVAREZ |
| Issued | 8/12/2024 | APPLICANT |
| CofO in Progress | 8/4/2025 | JOSE AVILA |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/1/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 8/1/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 8/5/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 8/6/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/22/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 10/22/2024 | Partial Approval | JOSE AVILA |
| Pre-Inspection | 10/22/2024 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 11/4/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 12/13/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 1/13/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 1/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 1/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 2/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 2/3/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 2/13/2025 | Approved | JOSE AVILA |
| Shower Pan | 3/14/2025 | No Access for Inspection | MICHAEL CORTEZ |
| Shower Pan | 3/17/2025 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 3/24/2025 | Approved | JOSE AVILA |
| Shower Pan | 3/24/2025 | Approved | JOSE AVILA |
| Sewer | 4/30/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/22/2025 | Corrections Issued | JOSE AVILA |
| Final | 6/4/2025 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 6/4/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 6/4/2025 | Approved | JOSE AVILA |
| Final | 8/1/2025 | OK to Issue CofO | JOSE AVILA |