19322 W CALVERT ST 91335

Certificate Information: 19322 W CALVERT ST 91335

Application / Permit
24010-20000-02982
Plan Check / Job No.
B24VN10145
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
<ePLAN> (N) 36'0"X51'9" IRREGULAR SHAPED PATIO & RECREATION ROOM ADDITION (INCLUDES HALF BATH AND AN OUTDOOR SHOWER) TO (E) REC ROOM
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
Issued on 5/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 MARVEL DELACRUZ
Corrections Issued 8/27/2024 MARVEL DELACRUZ
Quality Review Completed 9/4/2024 OMID HEDAYAT
Applicant returned to address corrections 2/27/2025 MARVEL DELACRUZ
Applicant returned to address corrections 3/19/2025 MARVEL DELACRUZ
Plan Check Approved 4/21/2025 MARVEL DELACRUZ
Issued 5/7/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/12/2024 CARLOS AGUILERA
Sewer availability Cleared 11/12/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/20/2024 CARLOS AGUILERA
Metro Rail approval Cleared 11/27/2024 JENNIFER SU
ZI Cleared 12/20/2024 ASHLEY RODARTE
Construction near power lines Cleared 12/23/2024 GEVORK KARAPETYAN
Construction within easement Cleared 12/23/2024 GEVORK KARAPETYAN
ZI Cleared 12/23/2024 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/30/2025 Corrections Issued SCOTT SOBEL
Deputy Drilled-In Anchors 7/2/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 9/3/2025 Partial Approval ALEXANDER HANDY
Deputy Reinf. Concrete 10/27/2025 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 11/5/2025 Partial Inspection ARUTYUN MADATYAN
Piling/Pier/Caisson 11/5/2025 Partial Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 12/23/2025 Corrections Issued ALEXANDER HANDY