5299 1/2 N CREBS AVE 91356

Certificate Information: 5299 1/2 N CREBS AVE 91356

Application / Permit
24010-20000-02940
Plan Check / Job No.
B24VN09979
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[N] DETACHED 2-STORY ADU (800 SQ.FT ) PER CA Govt. Code 65852.2(e)(1)(B). TYPE VA CONSTRUCTION
Permit Issued
Issued on 12/12/2024
Issuing Office
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 JOE VO
Corrections Issued 7/20/2024 JOE VO
Quality Review Completed 7/24/2024 GARO TELMI
Applicant returned to address corrections 8/22/2024 JOE VO
Plan Check Approved 10/3/2024 JOE VO
Issued 12/12/2024 APPLICANT
CofO in Progress 3/27/2026 JOHN KIDWELL
Permit Finaled 4/21/2026 JOHN JANSON
Permit Finaled 4/21/2026 JOHN JANSON
CofO Issued 4/21/2026 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/25/2024 JOE VO
Address approval Cleared 7/26/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/26/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/29/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/30/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 9/22/2024 RUEL COLE
Low Impact Development (LID) Cleared 9/24/2024 SARAH YOUSSEF

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/18/2024 Partial Approval JOHN KIDWELL
Underground Mechanical 1/2/2025 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 1/8/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 1/13/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 4/25/2025 Partial Inspection JOHN KIDWELL
HVAC-Rough 4/25/2025 Partial Inspection JOHN KIDWELL
PLUMBING-Rough 4/25/2025 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 7/2/2025 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 7/2/2025 Approved JOHN KIDWELL
HVAC-Rough 7/2/2025 Approved JOHN KIDWELL
PLUMBING-Rough 7/2/2025 Approved JOHN KIDWELL
Pre-Gunite 7/2/2025 Not Ready for Inspection JOHN KIDWELL
Rough-Elec/Plmb/HVAC 7/2/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 7/2/2025 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 7/14/2025 Partial Approval JOHN KIDWELL
Shower Pan 7/14/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 7/14/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/23/2025 Approved SEAN WIRCH
Insulation 7/23/2025 Approved SEAN WIRCH
Interior/Exterior Lathing 7/23/2025 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Not Ready for Inspection JOHN HAYES
Drywall Nailing 8/5/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Partial Inspection JOHN KIDWELL
Interior/Exterior Lathing 9/3/2025 Partial Approval GEVORK IPCHYAN
Final 2/17/2026 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 2/17/2026 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 2/17/2026 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved JOHN KIDWELL
Final 3/26/2026 OK to Issue CofO JOHN KIDWELL
Service/Power Release 3/26/2026 Approved JOHN KIDWELL