624-626 W 53RD ST 90037

Certificate Information: 624-626 W 53RD ST 90037

Application / Permit
24010-20000-02926
Plan Check / Job No.
B24VN09948
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLANl: NEW IRREGULAR SHAPED 94'-0" x 25'-0" 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE AND COVERED PORCH PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 12/16/2024
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 ALFRED RAMIREZ
Corrections Issued 7/22/2024 ALFRED RAMIREZ
Quality Review Completed 7/25/2024 STEVEN KIM
Plan Check Approved 12/5/2024 ALFRED RAMIREZ
Issued 12/16/2024 APPLICANT
CofO in Progress 6/4/2025 ALEJANDRO DE ARTOLA
Permit Finaled 6/5/2025 DEROLD HAUFF
CofO Issued 6/5/2025 DEROLD HAUFF
Permit Finaled 6/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/3/2024 CELINA MORENO
Sewer availability Cleared 9/3/2024 CELINA MORENO
Low Impact Development (LID) Cleared 9/12/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 10/10/2024 CELINA MORENO
Hydrant and Access approval Cleared 11/1/2024 JERRY KAO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/29/2025 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/29/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued SABAS ALONSO
Insulation 1/30/2025 Partial Approval SABAS ALONSO
Sewer 1/30/2025 Approved SABAS ALONSO
Underground Mechanical 1/30/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Approved BARRY HACHE
ELECTRICAL-Rough 3/17/2025 Approved SABAS ALONSO
PLUMBING-Rough 3/17/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 3/18/2025 Conditional Approval JOHN QUINTANILLA
Green Building Rough 3/18/2025 Approved JOHN QUINTANILLA
HVAC-Rough 3/18/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 3/18/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 3/20/2025 Approved ANTHONY RAMOS
Insulation 3/20/2025 Approved ANTHONY RAMOS
Drywall Nailing 3/26/2025 Approved SABAS ALONSO
Green Building Rough 3/26/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 3/26/2025 Approved SABAS ALONSO
ELECTRICAL-Final 6/2/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/2/2025 Approved ALEJANDRO DE ARTOLA
Final 6/3/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 6/3/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/3/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 6/3/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/3/2025 Approved ALEJANDRO DE ARTOLA