237-237 1/2 E 62ND ST 90003

Certificate Information: 237-237 1/2 E 62ND ST 90003

Application / Permit
24010-20000-02924
Plan Check / Job No.
B24VN09944
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLANl: NEW IRREGULAR SHAPED 90'-6" x 25'-0" 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE AND COVERED PORCH PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 12/6/2024
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 ALFRED RAMIREZ
Corrections Issued 7/21/2024 ALFRED RAMIREZ
Quality Review Completed 7/25/2024 STEVEN KIM
Plan Check Approved 11/19/2024 ALFRED RAMIREZ
Issued 12/6/2024 APPLICANT
CofO in Progress 5/20/2025 ALEJANDRO DE ARTOLA
Permit Finaled 6/3/2025 DEROLD HAUFF
Permit Finaled 6/3/2025 DEROLD HAUFF
CofO Issued 6/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 9/4/2024 CHRISTINA BRACO
Permit Cleared 9/4/2024 CHRISTINA BRACO
Sewer availability Cleared 9/4/2024 CHRISTINA BRACO
Low Impact Development (LID) Cleared 9/12/2024 ORVAL HERNANDEZ-MARCI
Trees in Parkway Cleared 9/30/2024 ADALBERTO VERA
Roof/Waste drainage to street Cleared 10/16/2024 CHRISTINA BRACO
Hydrant and Access approval Cleared 11/1/2024 JERRY KAO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/17/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/17/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/24/2025 Approved ALEJANDRO DE ARTOLA
Wood Frame 1/24/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/27/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 2/20/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/20/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 2/21/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Approved BARRY HACHE
ELECTRICAL-Rough 3/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/12/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/13/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/13/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 3/13/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 3/13/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/14/2025 Approved ALEJANDRO DE ARTOLA
Insulation 3/14/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 3/20/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/20/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/15/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/16/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/16/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/16/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 5/16/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/16/2025 Approved ALEJANDRO DE ARTOLA
Final 5/20/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 5/20/2025 Approved ALEJANDRO DE ARTOLA